Final | 10/4/2011 | 10/4/2011 | 10/4/2011 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Final | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | CANC |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino Inspection cancelled from web by: Debbie Marino
|
Rough-in | 8/5/2011 | 8/5/2011 | 8/5/2011 | P | PASS |
Troy James
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Rough-in | 8/4/2011 | 8/5/2011 | 8/5/2011 | A | FAIL |
Eric Strole
|
|
|
Building Energy will be there at 9:30 am on 8/5/11. Phone #: ###-#### >> Inspection requested via web by Debbie Marino-need heat sheild on b-vent 3rd flr, ductblast test pass
|
Rough-in | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | FAIL |
Eric Strole
|
|
|
Building Energy will perform the duct blast test at 9 am on 8/4/11. Phone #: ###-#### >> Inspection requested via web by Debbie Marino-9:00 am ductblast-no show, need revised manual j report on site
|
Pressure Test | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | PASS |
Eric Strole
|
|
|
Building Energy will perform the duct blast test at 9 am on 8/4/11. Phone #: ###-#### >> Inspection requested via web by Debbie Marino-20 lb test pass
|
Application received | | | 7/29/2011 | | DONE |
|
|
|
This permit was created on the web by Debbie Marino
|