Final | 12/16/2011 | 12/16/2011 | 12/16/2011 | P | PASS |
Bill VanDegrift
|
|
|
oleg Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/16/2011 | | DONE |
|
|
|
Payment received via Govolutions
|
Fees Due Hold | 12/9/2011 | | 12/16/2011 | | DONE |
|
|
|
|
Final | 12/7/2011 | 12/8/2011 | 12/8/2011 | A | FAIL |
Alan Hauser
|
|
|
equipment doesn't meet approved manual J report
|
Reinspection Fee (no hold) | 12/8/2011 | 12/8/2011 | 12/8/2011 | P | PASS |
Alan Hauser
|
|
|
correction not finished from r/i
|
Rough-in | 9/16/2011 | 9/16/2011 | 9/16/2011 | A | PART |
Bill VanDegrift
|
|
|
ok to cover needs equipment changed out by final
|
Rough-in | 9/13/2011 | 9/14/2011 | 9/14/2011 | A | PART |
Jim Johnson
|
|
|
Late morning please---Oleg Phone #: ###-#### gas test test ok 30# still need to correct equipment to match design
|
Rough-in | 9/12/2011 | 9/13/2011 | 9/13/2011 | A | FAIL |
Bill VanDegrift
|
|
|
r/i and duct blast //9am please//call before//Oleg Phone #: ###-#### equipment does not match design and gas test failed
|
Rough-in | 9/8/2011 | 9/9/2011 | 9/9/2011 | P | FAIL |
Dixie Fellows
|
|
|
oleg Phone #: ###-####...no inspections until fees are paid...no duct blaster scheduled
|
Application received | | | 9/8/2011 | | |
|
|
|
|
Issue permit | | | 9/8/2011 | | DONE |
|
|
|
|