Final | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Eric Strole
|
|
|
Please complete a final re-inspection. If there are any questions/concerns, please contact Eric @ ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan
|
Final | 12/12/2011 | 12/14/2011 | 12/14/2011 | P | FAIL |
Bill VanDegrift
|
|
|
Please complete a final inspection. If there are any questions/concerns, please contact Eric @ ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan combustion air required for basement furnace picked up air balance report.
|
Pressure Test | 12/5/2011 | 12/5/2011 | 12/5/2011 | P | PASS |
Dixie Fellows
|
|
|
Please complete an underground gas pressure test. If there are any issues/questions, please contact Eric @ ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan...u/g test to fire-pit ok..1" at 20lbs
|
Pressure Test | 12/2/2011 | 12/5/2011 | 12/5/2011 | A | FAIL |
Dixie Fellows
|
|
|
Please complete an underground gas pressure test. If there are any issues/questions, please contact Eric @ ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan...need btu load
|
Pressure Test | 12/2/2011 | 12/5/2011 | 12/2/2011 | P | CANC |
Dixie Fellows
|
|
|
Please complete an underground gas pressure test. If there are any questions or concerns, please contact Eric @ ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan Inspection cancelled from web by: Jennifer Bryan
|
Rough-in | 10/12/2011 | 10/13/2011 | 10/13/2011 | P | PASS |
Eric Strole
|
|
|
This is a request for a re-inspection. If there are any questions or on site issues, please contact Eric at ###-####. (SR 52/04) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan
|
Rough-in | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | FAIL |
Dixie Fellows
|
|
|
please complete a reinspection on the rough in only. call eric with any issues Phone #: ###-#### >> Inspection requested via web by Alana Lane...I need Eric to meet me at this job Wed am to discuss C/N...Thanks Dixie
|
Rough-in | 10/10/2011 | 10/10/2011 | 10/10/2011 | A | FAIL |
Eric Strole
|
|
|
r/i..gas test..duct blaster..plz meet matt at 11:00-20 lb gas test & duct blast pass. need manual j report on site for rough-in.
|
Rough-in | 10/7/2011 | 10/10/2011 | 10/10/2011 | A | NR |
Dixie Fellows
|
|
|
please complete rough in & pressure test inspection. please contact eric with any issues ###-#### Phone #: ###-#### >> Inspection requested via web by Alana Lane...need to schedule the duct blaster
|
Issue permit | | | 10/7/2011 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/7/2011 | | DONE |
|
|
|
This permit was created on the web by Alana Lane
|