Final | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | PASS |
Troy James
|
|
|
>> Inspection requested via web by Dustin Rich
|
Final | 1/20/2012 | 1/20/2012 | 1/20/2012 | P | FAIL |
Eric Strole
|
|
|
>> Inspection requested via web by Dustin Rich-Not ready for final, need to be complete with sheetrock,doors,registers and grills and stove and water heater flue, air balance report and all other parts of the heating and cooling system.
|
Rough-in | 1/13/2012 | 1/13/2012 | 1/13/2012 | P | PASS |
Troy James
|
|
|
Check correct furnace installation at final and combustion air, submitted revised manaul j report
|
Rough-in | 1/6/2012 | 1/9/2012 | 1/9/2012 | A | FAIL |
Eric Strole
|
|
|
>> Inspection requested via web by Dustin Rich-There is no approved coil on manual j report and manual j needs to be approved by troy james.
|
Pressure Test | 1/6/2012 | 1/9/2012 | 1/9/2012 | A | PASS |
Eric Strole
|
|
|
>> Inspection requested via web by Dustin Rich-20 lb gas test pass.
|
Issue PAID IN FULL permit | | | 12/29/2011 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/29/2011 | | DONE |
|
|
|
This permit was created on the web by Dustin Rich
|