Final | 9/7/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Dixie Fellows
|
|
|
###-####
|
Conference | 6/6/2012 | 6/7/2012 | 6/7/2012 | A | PASS |
Dixie Fellows
|
|
|
8:45 meet contractor to discuss mantles...mantle and corbels meet manuf specs
|
Conference | 6/6/2012 | 6/6/2012 | 6/6/2012 | P | PEND |
Dixie Fellows
|
|
|
Contact Ryan with any questions. We are requesting a look at the Height of the mantel.. Thank you Phone #: ###-#### >> Inspection requested via web by Rhonda Marcum...this should have scheduled for thurs am...i rescheduled this
|
Rough-in | 5/14/2012 | 5/15/2012 | 5/15/2012 | A | PASS |
Dixie Fellows
|
|
|
rEQUESTING A ROUGH IN AND FINAL FOR FIREPLACES ANY QUESTIONS PLS CONYACT RYAN AT ###-#### Phone #: ###-#### >> Inspection requested via web by Rhonda Marcum...all 3 wood burners ok
|
Issue PAID IN FULL permit | | | 5/14/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/11/2012 | | DONE |
|
|
|
This permit was created on the web by Rhonda Marcum
|