Final | 6/25/2014 | 6/27/2014 | 6/27/2014 | A | PASS |
Alan Hauser
|
|
|
|
Rough-in | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PASS |
Chad Schwendiman
|
|
|
Rough in for cover. Contact Bryon ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty - Okay to cover ceilings
|
Rough-in | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Chad Schwendiman
|
|
|
Brian Phone #: ###-#### >> Inspection requested via web by Michele LaMott - Trama, & patiant rooms ok cover.
|
Rough-in | 4/29/2014 | 4/30/2014 | 4/30/2014 | A | PART |
Alan Hauser
|
|
|
duct sealed, ok for insulation
|
Rough-in | 4/14/2014 | 4/15/2014 | 4/15/2014 | A | PART |
Alan Hauser
|
|
|
ok to insulate duct, duct has been sealed
|
Rough-in | 4/8/2014 | 4/8/2014 | 4/8/2014 | A | PART |
Alan Hauser
|
|
|
two s/f dampers appear to be installed as per manufacture
|
Rough-in | 1/30/2014 | 1/31/2014 | 1/31/2014 | A | PART |
Alan Hauser
|
|
|
Soiled Utility Room. ok, signed occ. card for this room
|
Rough-in | 12/23/2013 | 12/23/2013 | 12/23/2013 | P | PASS |
Troy James
|
|
|
Contact Stan Lillquist ###-####. Phase 2b, waiting and Staff lounge. Jim Martin ###-#### with Anderson is requesting someone to sign his card for Temp Occcupancy. Phone #: ###-#### >> Inspection requested via web by Dan Flaherty Ok to occupy phase 2B and staff lounge.
|
Rough-in | 12/17/2013 | 12/18/2013 | 12/18/2013 | A | PASS |
Troy James
|
|
|
Cover inspection in phase 2b, waiting and staff lounge. Contact Ben Livingston ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty ok to cover
|
Rough-in | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | PASS |
Alan Hauser
|
|
|
Alan, Anderson Constructions Super Jim Martin ###-#### is requesting that you come by and sign his card for this Rough-in Temp Occupancy for Temp Exam Rms. He does not like the email of approval I forwarded to him from Boise City. Dan Flaherty ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty SIGNED CARD
|
Rough-in | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Alan Hauser
|
|
|
Rough-in Temp Occupancy for Temp Exam Rms ok for temp occ.
|
Rough-in | 11/26/2013 | 11/27/2013 | 11/27/2013 | A | NH |
Bill VanDegrift
|
|
|
Rough-in / temp occupancy for the Temp Exam room. Contact Ben Livingston ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty talked to Ben He was going to check into what they wanted and call me back, never gat a call
|
Rough-in | 11/6/2013 | 11/7/2013 | 11/7/2013 | A | PART |
Alan Hauser
|
|
|
Rough in phase 2B. Contact Stan ###-#### or Ben ###-#### dcut ok for cover
|
Rough-in | 8/20/2013 | 8/22/2013 | 8/22/2013 | A | PART |
Alan Hauser
|
|
|
final phase 2
|
Rough-in | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | CANC |
Bill VanDegrift
|
|
|
Rough in for area 2A Contact Ben at ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty Alan rescheduled for Thursday
|
Rough-in | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PASS |
Troy James
|
|
|
Contact Ben Livingston ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty ok to insulate ducts to area front of hospital
|
Rough-in | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PASS |
Alan Hauser
|
|
|
FINAL FOR PHASE 1 ONLY
|
Rough-in | 1/24/2013 | 1/25/2013 | 1/25/2013 | A | PART |
Alan Hauser
|
|
|
ok to insulate duct
|
Issue PAID IN FULL permit | | | 11/9/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/9/2012 | | DONE |
|
|
|
This permit was created on the web by Dan Flaherty
|