Final | 5/17/2013 | 5/20/2013 | 5/20/2013 | A | PASS |
Alan Hauser
|
|
|
|
Rough-in | 5/8/2013 | 5/9/2013 | 5/9/2013 | A | PASS |
Alan Hauser
|
|
|
all areas ok for cover
|
Rough-in | 3/12/2013 | 3/12/2013 | 3/12/2013 | A | PASS |
Alan Hauser
|
|
|
all hydronic piping ok and tested
|
Rough-in | 3/8/2013 | 3/11/2013 | 3/11/2013 | A | PASS |
Alan Hauser
|
|
|
all hvac complete, recall when grid is in before tile
|
Rough-in | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | PART |
Alan Hauser
|
|
|
duct ok for insulation
|
Issue PAID IN FULL permit | | | 1/10/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/10/2013 | | DONE |
|
|
|
This permit was created on the web by Rhonda Marcum
|
First Notice | 5/20/2013 | 5/20/2013 | | | |
Alan Hauser
|
|
|
|