Print Statement | | | 11/8/2013 | | DONE |
|
|
|
|
First Notice | 8/15/2013 | 8/15/2013 | 10/8/2013 | | DONE |
Alan Hauser
|
|
|
|
Final | 8/13/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Alan Hauser
|
|
|
|
Final | 8/13/2013 | 8/14/2013 | 8/15/2013 | P | PASS |
Alan Hauser
|
|
|
|
Rough-in | 7/23/2013 | 7/23/2013 | 7/23/2013 | P | PART |
Alan Hauser
|
|
|
two 2nd floor west shafts ok for cover and center rooms with grid ok for cover
|
Rough-in | 7/16/2013 | 7/17/2013 | 7/17/2013 | A | PART |
Dixie Fellows
|
|
|
rough in cover Bodybuilding.com mike ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs...ok for cover restrooms 2nd floor s/w corner
|
Rough-in | 7/3/2013 | 7/3/2013 | 7/3/2013 | P | PASS |
Troy James
|
|
|
Grease Duct Inspection - Fire Wrap Inspection. Contact Mike Graves Phone #: ###-#### >> Inspection requested via web by Allison Briggs ok first layer grease duct
|
Rough-in | 7/1/2013 | 7/2/2013 | 7/2/2013 | A | PART |
Alan Hauser
|
|
|
ok for cover on west end and west bathrooms on 2nd floor
|
Rough-in | 6/18/2013 | 6/19/2013 | 6/19/2013 | A | PASS |
Troy James
|
|
|
bodybuilding.com rough ###-#### Phone #: ###-#### >> Inspection requested via web by Allison Briggs Ok fire dampers at east wall second floor and restroom ok to cover east wall second floor. Discussed solutions for grease duct west side. Need to have approved rated shaft built or fire wrap grease duct. Currently do not have enough room to do either.
|
Rough-in | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | PART |
Alan Hauser
|
|
|
shaft 1st floor s.e. corner ok for cover
|
Rough-in | 5/14/2013 | 5/15/2013 | 5/15/2013 | A | PART |
Alan Hauser
|
|
|
1st floor locker area ok for cover
|
Rough-in | 5/9/2013 | 5/10/2013 | 5/10/2013 | A | PART |
Alan Hauser
|
|
|
kitchen area basement s.e. corner ok for cover
|
Rough-in | 5/6/2013 | 5/7/2013 | 5/7/2013 | A | PART |
Alan Hauser
|
|
|
s.w. corner basement soffit ok for cover
|
Rough-in | 5/1/2013 | 5/2/2013 | 5/2/2013 | A | PART |
Alan Hauser
|
|
|
Bodybuilding.com Rough In 1st Floor South East Corner bathroom to cover ok to cover
|
Rough-in | 4/18/2013 | 4/19/2013 | 4/19/2013 | A | PART |
Alan Hauser
|
|
|
four bathrooms in basement ok for cover
|
Rough-in | 4/8/2013 | 4/9/2013 | 4/9/2013 | A | PART |
Alan Hauser
|
|
|
Bodybuilding.com Shaft Fire Wrap Inspection - Contact Steve ###-####, for location Phone #: ###-#### >> Inspection requested via web by Allison Briggs conference on grease duct in 2hr. shaft. need minimum 6" clearance all sides
|
Issue PAID IN FULL permit | | | 4/1/2013 | | DONE |
|
|
|
|
Application received | | | 3/20/2013 | | DONE |
|
|
|
This permit was created on the web by Allison Briggs
|