(F) Reprint permit | | | 2/7/2014 | | DONE |
|
|
|
|
First Notice | 7/26/2013 | 7/26/2013 | 1/10/2014 | | DONE |
Troy James
|
|
|
This permit finaled on the web by Nicholas Paige // final value calcd in combination with Plm13-00335
|
Final | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | PASS |
Troy James
|
|
|
Will resubmit plan mod for smoke detectors at each return inlet. Fire inspector will look at smoke detectors.
|
Final | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | FAIL |
Troy James
|
|
|
please call john with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Plan mod approved by fire plan reviewer has been approved without given full information. Plan mod is now not approved. Cannot approve final until the smoke detector to heat pumps design has been approved. We have open return serving three separate areas.
|
Final | 7/17/2013 | 7/19/2013 | 7/22/2013 | A | FAIL |
Troy James
|
|
|
please call John with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Need smoke detectors to 3 mechanical units north east side of building.
|
Pressure Test | 6/24/2013 | 6/24/2013 | 6/24/2013 | P | PART |
Alan Hauser
|
|
|
Hydronic Pressure Test ok on all above ground hydronics
|
Conference | 6/21/2013 | 6/21/2013 | 6/21/2013 | A | PART |
Bill VanDegrift
|
|
|
will need RTU's for ventilation
|
Rough-in | 6/18/2013 | 6/18/2013 | 6/18/2013 | P | PART |
Dixie Fellows
|
|
|
please call Doran with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige...OK TO COVER HYDRONICS IN ALL WALLS
|
Rough-in | 6/7/2013 | 6/11/2013 | 6/11/2013 | A | PART |
Troy James
|
|
|
please call john with any questions, this is a cover inspection Phone #: ###-#### >> Inspection requested via web by Nicholas Paige ok to cover hard lid and walls only
|
Rough-in | 5/29/2013 | 5/29/2013 | 5/29/2013 | P | PASS |
Dixie Fellows
|
|
|
Partial cover inspection Phone #: ###-#### >> Inspection requested via web by Nicholas Paige..ok to wrap
|
Rough-in | 4/16/2013 | 4/17/2013 | 4/18/2013 | P | PASS |
Dixie Fellows
|
|
|
please call doran with any questions. this is a rough in for underground radiant tubing Phone #: ###-#### >> Inspection requested via web by Nicholas Paige...100lb test on remaining u/g tubing ok
|
Rough-in | 4/4/2013 | 4/4/2013 | 4/4/2013 | P | PART |
Bill VanDegrift
|
|
|
This is for the in floor radiant tubing rough in please call doran with any questions! Phone #: ###-#### >> Inspection requested via web by Nicholas Paige 4 - radiant test ok
|
Issue PAID IN FULL permit | | | 4/4/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 4/3/2013 | | |
|
|
|
|
Application received | | | 4/3/2013 | | DONE |
|
|
|
This permit was created on the web by Nicholas Paige
|