Pressure Test | 6/3/2013 | 6/4/2013 | 6/4/2013 | P | PASS |
Troy James
|
|
|
20# test
|
Final | 6/4/2013 | 6/4/2013 | 6/4/2013 | P | PASS |
Troy James
|
|
|
|
Pressure Test | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | CANC |
Eric Strole
|
|
|
Pressure test will be ready by 10 am at the latest. Sorry for the mess on Monday am. Thanks. Scott. Phone #: ###-#### >> Inspection requested via web by Scott Sparrell
|
Pressure Test | 5/31/2013 | 6/3/2013 | 6/3/2013 | A | NR |
Eric Strole
|
|
|
|
Rough-in | 5/30/2013 | 5/31/2013 | 5/31/2013 | P | PART |
Eric Strole
|
|
|
Scott is contact Phone #: ###-#### >> Inspection requested via web by Scott Sparrell-ok to cover, still need test
|
Issue PAID IN FULL permit | | | 5/30/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/30/2013 | | DONE |
|
|
|
This permit was created on the web by Scott Sparrell
|