Final | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Konrad Swartz
|
Rough-in | 6/21/2013 | 6/21/2013 | 6/21/2013 | P | PASS |
Eric Strole
|
|
|
BVENT is Framed now >> Inspection requested via web by Konrad Swartz
|
Rough-in | 6/19/2013 | 6/19/2013 | 6/19/2013 | P | FAIL |
Bill VanDegrift
|
|
|
Rough in mech reinspect w/ gas >> Inspection requested via web by Konrad Swartz install required 10" to loft, frame around the b-vent on the second floor. need to resubmit ACCA report for loft design.
|
Rough-in | 6/17/2013 | 6/17/2013 | 6/17/2013 | P | FAIL |
Eric Strole
|
|
|
Rough in Mech with Gas Pressure Re-inspection Phone #: ###-#### >> Inspection requested via web by Konrad Swartz-Need finish rough-in. (crawl)
|
Rough-in | 6/14/2013 | 6/17/2013 | 6/17/2013 | A | FAIL |
Eric Strole
|
|
|
Rough in Mech with Gas pressure Phone #: ###-#### >> Inspection requested via web by Konrad Swartz-20 lb gas test pass, need approved manual-j on site for rough-in inspection.
|
Issue PAID IN FULL permit | | | 6/13/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/13/2013 | | DONE |
|
|
|
This permit was created on the web by Konrad Swartz
|