Final | 8/12/2013 | 8/13/2013 | 8/13/2013 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brad Allison
|
Final | 8/8/2013 | 8/8/2013 | 8/8/2013 | P | FAIL |
Bill VanDegrift
|
|
|
adjust furnace to get close to design--redo air balance.
|
Rough-in | 8/7/2013 | 8/8/2013 | 8/8/2013 | A | FAIL |
Alan Hauser
|
|
|
this house is sheetrocked
|
Rough-in | 7/9/2013 | 7/10/2013 | 7/10/2013 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brad Allison-20 lb gas test and r/i pass. (check for damper in bonus room on final)
|
Rough-in | 7/3/2013 | 7/9/2013 | 7/9/2013 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brad Allison-20 lb gas test pass, return and wall stacks and boots are undersized per manual-j and need to frame in b-vent and need to insulate supply in back of house that is in unconditioned space.
|
Rough-in | 7/2/2013 | 7/3/2013 | 7/3/2013 | P | CANC |
Eric Strole
|
|
|
Late in the day if possible please. Phone #: ###-#### >> Inspection requested via web by Brad Allison Inspection cancelled from web by: Brad Allison
|
Issue PAID IN FULL permit | | | 7/1/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/1/2013 | | DONE |
|
|
|
This permit was created on the web by Brad Allison
|