Final | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | PASS |
Chad Schwendiman
|
|
|
final - warehouse Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen
|
Rough-in | 1/8/2014 | 1/9/2014 | 1/9/2014 | A | PART |
Alan Hauser
|
|
|
ok for tile 2nd floor
|
Rough-in | 12/20/2013 | 12/23/2013 | 12/23/2013 | A | PASS |
Troy James
|
|
|
Partial Cover for 1st floor and stairs Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen ok cover ceilings first floor
|
Rough-in | 9/24/2013 | 9/25/2013 | 9/25/2013 | A | PART |
Alan Hauser
|
|
|
hvac duct ok, recall when grid is in. all hard ceiling areas ok for cover.
|
Rough-in | 9/20/2013 | 9/23/2013 | 9/23/2013 | A | PEND |
Eric Strole
|
|
|
Hard lid cover inspection 1st & 2nd floor Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen- There is a stop work on project. No inspections till stop work is lifted.
|
Issue PAID IN FULL permit | | | 8/22/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/22/2013 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|
First Notice | 3/19/2014 | 3/19/2014 | | | |
Chad Schwendiman
|
|
|
|