First Notice | 10/10/2013 | 10/10/2013 | 12/12/2013 | | DONE |
Troy James
|
|
|
|
Final | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PASS |
Troy James
|
|
|
randy Phone #: ###-####
|
Rough-in | 10/3/2013 | 10/3/2013 | 10/3/2013 | P | PASS |
Troy James
|
|
|
2nd layer of fire wrap inspection please-Randy Phone #: ###-####
|
Conference | 10/2/2013 | 10/2/2013 | 10/2/2013 | P | DONE |
Troy James
|
|
|
|
Rough-in | 10/2/2013 | 10/2/2013 | 10/2/2013 | P | PART |
Eric Strole
|
|
|
Randy-Inspection of 1st layer of fire wrap on grease duct please Phone #: ###-####-1st layer of fire wrap pass.
|
Rough-in | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | PART |
Alan Hauser
|
|
|
light test ok for grease duct
|
Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PART |
Dixie Fellows
|
|
|
light test on grease duct// Randy Phone #: ###-####...6' of solid grease duct ok for light test
|
Issue PAID IN FULL permit | | | 9/23/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Issue PAID IN FULL permit | | | 9/23/2013 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/23/2013 | | DONE |
|
|
|
|
Application received | | | 9/23/2013 | | |
|
|
|
|