CHANGE STATUS TO (FNL) | | | 1/27/2014 | | DONE |
Christina Prado
|
|
|
Per Dixie - permit finaled 1/14/14, didn't doc final orig
|
Final | 1/14/2014 | 1/14/2014 | 1/14/2014 | P | PASS |
Dixie Fellows
|
|
|
FINAL
|
Final | 1/9/2014 | 1/10/2014 | 1/10/2014 | A | PART |
Dixie Fellows
|
|
|
please call John with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige...TEMP OK...WAITING ON OTHER MECHANICAL CONTRACTOR TO SCHEDULE THEIRS
|
Rough-in | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | PASS |
Dixie Fellows
|
|
|
this is a cover inspection. Please call John with any questions. Phone #: ###-#### >> Inspection requested via web by Nicholas Paige..all grid ok for cover
|
Rough-in | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | PASS |
Dixie Fellows
|
|
|
please call John with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige..all ductwork only for cover
|
Rough-in | 11/26/2013 | 11/26/2013 | 11/26/2013 | A | PART |
Bill VanDegrift
|
|
|
this is a partial cover inspection. please call John with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige retail area ok for grid
|
Issue PAID IN FULL permit | | | 11/25/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/25/2013 | | DONE |
|
|
|
This permit was created on the web by Nicholas Paige
|