First Notice | 11/9/2016 | 11/9/2016 | 7/27/2020 | | DONE |
Troy James
|
|
|
This permit finaled on the web by RM Mechanical
|
Print Statement | | | 4/26/2018 | | DONE |
|
|
|
|
Print Statement | | | 4/16/2018 | | DONE |
|
|
|
|
Final | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | PASS |
Troy James
|
|
|
Onsite contact: Jason Davidson. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Final | 10/28/2016 | 10/31/2016 | 10/31/2016 | A | FAIL |
Troy James
|
|
|
Onsite contact: Jason Davidson Phone #: ###-#### Inspection requested via web by Melissa Kaae Last portion of boiler flues before it goes vertical to exterior needs to grade at 1/4" per foot.
|
Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | FAIL |
Troy James
|
|
|
Onsite contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae Need air balance report for garage exhaust, FSD at dust collection room and flue cap installed to boiler flues.
|
Rough-in | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PASS |
Troy James
|
|
|
EF-106. Onsite contact: Jason Davidson. Phone #: ###-#### Inspection requested via web by Melissa Kaae basement exhaust from front st side up to first floor shaft grid 8 and 9. Open shaft to exterior grille.
|
Mec-Aging Inspection | 7/22/2016 | 7/22/2016 | 7/27/2016 | | PEND |
Troy James
|
|
|
work in progress
|
Mec-Aging Inspection | 4/22/2016 | 4/22/2016 | 4/22/2016 | | PEND |
Troy James
|
|
|
waiting for contractor to complete work
|
Mec-Aging Inspection | 1/22/2016 | 1/22/2016 | 1/22/2016 | | PEND |
Troy James
|
|
|
wip
|
Rough-in | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PART |
Troy James
|
|
|
Approval for cover. On site contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae ok underground duct under office building
|
Rough-in | 10/20/2015 | 10/21/2015 | 10/21/2015 | A | DEFR |
Troy James
|
|
|
Approval for cover. On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Scheduled inpsection for underground parking for the simplot office buiding. Need to pull new permit.
|
Mec-Aging Inspection | 9/8/2015 | 9/8/2015 | 9/8/2015 | | PEND |
Troy James
|
|
|
wip
|
Mec-Aging Inspection | 6/9/2015 | 6/9/2015 | 6/10/2015 | | DONE |
Troy James
|
|
|
work in progress
|
Rough-in | 2/5/2015 | 2/5/2015 | 2/9/2015 | P | PART |
Troy James
|
|
|
set up my own inspection to walk the parking garage
|
Conference | 1/8/2015 | 1/8/2015 | 1/9/2015 | P | DONE |
Troy James
|
|
|
Met with rita. She will transfer notes from the shell and core permit to the parking underground parking garage permit.
|
Conference | 1/6/2015 | 1/6/2015 | 1/8/2015 | P | PASS |
Troy James
|
|
|
need to contact contractor as no inspections have been requested
|
Rough-in | 8/13/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Troy James
|
|
|
This inspection was done under mec13-05287. 5th floor ok two air handlers at garage tie ins. rad
|
Rough-in | 7/29/2014 | 7/30/2014 | 7/31/2014 | A | PASS |
Troy James
|
|
|
This inspection was done under mec13-05287. Basement and amp 4th floor.rad
|
Rough-in | 7/16/2014 | 7/9/2014 | 7/9/2014 | A | PART |
Troy James
|
|
|
This inspection was done under mec13-05287 Looked at fsd to shafts in basement. Not complete inspections.rad
|
Rough-in | 12/27/2013 | 12/30/2013 | 12/30/2013 | A | PART |
Troy James
|
|
|
Inspection done under mec13-05287//rough in for cover. ok to cover ducts in concreted chase/column east side of building that go from basement to the 3rd level. no fire damper at this time where ducts penetrates the garage ceiling.rad
|
Issue PAID IN FULL permit | | | 12/13/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/13/2013 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|