Permit Information
Permit NumberMEC13-05287
StatusFinaled
Name RM MECHANICAL
Site Address 1000 W MYRTLE ST
Project Name 
Customer NumberD13-015
ePlanReviewNo
Description
Mechanical Permit - New: Install HVAC ductwork & equipment for the structure.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice1/12/20171/12/20177/27/2020 DONE
DetailsTroy James
This permit finaled on the web by RM Mechanical
Final1/12/20171/13/20171/12/2017APASS
DetailsTroy James
Onsite contact: Jason Davidson Phone #: ###-#### Inspection requested via web by Melissa Kaae
Final10/20/201610/21/201610/21/2016AFAIL
DetailsTroy James
Onsite contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae
Need FSD installed at duct penetrating the dust collection room exterior wall.
Mec-Aging Inspection7/28/20167/28/20167/28/2016 PEND
DetailsTroy James
Talked to contractor. He is going to check into the makers studio to see if final can be done.
Rough-in4/28/20164/29/20164/29/2016APASS
DetailsTroy James
Valet bathroom
Approval for cover
Ben Skelton ###-####

Phone #: ###-#### Inspection requested via web by Melissa Kaae
ok to cover ceiling, access door required at ceiling to access equipment above
Mec-Aging Inspection2/22/20162/22/20162/22/2016 PEND
DetailsTroy James
waiting for the air balance for kichen hood first floor and makers studio to be finaled
Mec-Aging Inspection11/23/201511/23/201511/23/2015 PEND
DetailsTroy James
wip
Final8/24/20158/25/20158/26/2015APART
DetailsTroy James
Final for roof only. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
ok fan and duct on roof. roof is complete
Final8/10/20158/11/20158/11/2015AFAIL
DetailsTroy James
On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
Ok temp occupancy. Need some ductwork done on roof and makers studio to be completed.
Final7/8/20157/9/20157/9/2015AFAIL
DetailsTroy James
On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
Corrections posted with Ben
Rough-in6/22/20156/22/20156/23/2015PFAIL
DetailsTroy James
Fireplace finalization. On site contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae
Still need approval from manufacturer ok for contractor to not pipie the convection pipe to adjacent room.
Conference6/18/20156/18/20156/18/2015ADONE
DetailsTroy James
Conference inspection to fireplace installation compliance. Informed contractor to contact manufacturer for approval. Contractor does not want to install convection duct to interior wall per JUMP requests.
Final6/4/20156/5/20156/5/2015ANR
DetailsTroy James
6th floor kitchen // Ben Phone #: ###-####
no final at this time
Rough-in6/5/20156/5/20156/5/2015PPASS
DetailsTroy James
6th floor kitchen // Ben Phone #: ###-####
ok to cover kitchen area
Rough-in4/13/20154/14/20154/14/2015APART
DetailsTroy James
6th floor kitchen, approval for cover. On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
Need to insulate grease duct at hood connection.
Rough-in2/27/20152/27/20152/27/2015PPASS
DetailsTroy James
JUMP Lobby. On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
0k cover 5th floor lobby
Rough-in2/18/20152/19/20152/19/2015APASS
DetailsTroy James
Pioneer lobby, 6th floor. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
Ok to cover ceiling in the pioneer room
Rough-in2/4/20152/5/20152/9/2015PFAIL
DetailsTroy James
6th floor: Bathrooms ; Pioneer Lobby. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
6th floor ok to cover at bathrooms and lobby.
Need to install outside air duct at air handler to the makers studio to the street side as per approved drawings. The daiken ductless units need to have the condensate drain installed and terminate to an approved location.
Case Summary (MEC)  1/8/2015 DONE
DetailsChristina Prado
Rough-in12/17/201412/18/201412/18/2014APASS
DetailsTroy James
5th floor bathrooms. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
ok ceiling cover 5th floor restrooms and movement room
Rough-in12/5/201412/8/201412/8/2014APASS
DetailsTroy James
ok wood ceiling cover at second floor. Ok large duct cover from air handler on roof to inside of buiding at 6th floor.
Rough-in12/4/201412/5/201412/5/2014ACANC
DetailsTroy James
Approval for cover 2nd floor ; 6th floor. Onsite contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae
rescheduled inspection for monday morning
Rough-in11/10/201411/12/201411/12/2014APASS
DetailsTroy James
Ceiling inspection, levels 5 & 6. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover insulate supply runs at 6th kitchen and fsd at 1st floor garage exhaust west side
Rough-in10/16/201410/17/201410/17/2014APASS
DetailsTroy James
Re-inspect 5th floor / mech case, Makers Studio. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover chase at makers studio and ok to insulate ducts at 6th floor.
Rough-in10/15/201410/16/201410/16/2014APART
DetailsTroy James
4th floor restroom & re-inspection for Makers Studio mech case for duct collator (also on 4th floor). Onsite contact: Rob Butler. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
Ok to cover ceiling at 4th floor restrooms after access door is framed for access to motor at fire damper. Need to remove rubber gasket at dust collector floor sweep and install approved materials.
Rough-in10/1/201410/2/201410/2/2014AFAIL
DetailsTroy James
5th floor HVAC rough-in. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
Need to change the floor sweep with a 45 degree tap. Duct collector to laser room may need explosion relief venting.
Rough-in9/25/20149/26/20149/26/2014APASS
DetailsTroy James
Mechanical case inspection, 5th floor. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
ok ducts from air handler through shaft to 5th floor and exhaust duct in shaft from 5th to the roof.
Rough-in9/22/20149/23/20149/23/2014PFAIL
DetailsTroy James
Fire smoke dampers 3rd ; 5th floors. Onsite contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae
need 1/8" per foot of damper gap between damper sleeve and framing.
Rough-in9/4/20149/5/20149/5/2014PPART
DetailsTroy James
2nd floor ceiling cover. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae
Ok to cover hard lid ceilings. Contractor will schedule another inspection for tuesday to inspect more ducts being installed for insulation.
Rough-in8/14/20148/15/20148/15/2014APASS
DetailsTroy James
Rough-in for 5th floor maker studio & 2nd floor restrooms. Onsite contact: Rob Butler Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover the spray booth duct with fire wrap and ok the dryer duct at makers studio
Rough-in8/13/20148/13/20148/13/2014PPASS
DetailsTroy James
5th floor // Ben Phone #: ###-####
no inspection on 5th floor. Ok two air handlers at garage tie ins. Ok to cover 1st floor hard lid ceiling.
Rough-in8/6/20148/6/20148/6/2014PFAIL
DetailsTroy James
Rough-In 2nd Floor. Onsite Contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
need 24x24 access doors to fan coil units and two 18x18 access doors under the fire smoke dampers at shaft. Also waiting to here from the structural engineer in regards to the hangers for the fan coil units.
Rough-in7/29/20147/30/20147/31/2014PPASS
DetailsTroy James
Basement & 4th floor restroom. Onsite contact: Ben Skelton Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover restroom and inspiration room.
Rough-in7/16/20147/17/20147/17/2014PFAIL
DetailsTroy James
Grease duct 1st floor & 1st floor restroom. Onsite contact: Ben Skelton Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover grease duct.
Access doors are not installed correctly. Need to install per ICC esr report.
Rough-in7/8/20147/9/20147/9/2014APART
DetailsTroy James
Looked at fsd to shafts at basement. Not complete inspection.
Rough-in7/7/20147/8/20147/8/2014PCANC
DetailsTroy James
4th floor & basement rough-in. Onsite contact Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
reschedule for morning
Rough-in6/10/20146/11/20146/11/2014APASS
DetailsTroy James
3rd floor media studio, underfloor duct. Approve for insulation cover. Onsite contact: Rob Butler Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to insulate ducts under the media room
Rough-in6/2/20146/3/20146/3/2014APART
DetailsTroy James
Tom-lite test Phone #: ###-####
ok light test to portion of grease duct pioneer kitchen
Rough-in5/28/20145/29/20145/29/2014APART
DetailsTroy James
Kitchen studio, 2 each, 1st & 2nd floor. Shaft, approve for cover. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover shafts, still need to inspect fsd at basement when ducts enter the shaft
Rough-in5/28/20145/28/20145/28/2014PPART
DetailsTroy James
Multimedia center wall approve for cover. Duct in walls approve for cover. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok ducts in wall at media room, ok to cover shafts west and east at frontier room, still need to inspect fsd where ducts enter shaft from basement, Need to know why vav boxes are not being hung per plans
Pressure Test5/20/20145/21/20145/21/2014PPART
DetailsChad Schwendiman
MEC-COM/RES INSPECTOR - LIGHT TEST FOR KITCHEN STUDIO HOOD GREASE DUCT IN SHAFT PASS.
Rough-in5/20/20145/21/20145/21/2014PPART
DetailsChad Schwendiman
MEC-COM/RES INSPECTORN - DUCT APPROVED FOR WRAP NORTH SIDE OF MULTI MEDIA SOFFIT.
Pressure Test5/13/20145/14/20145/14/2014AFAIL
DetailsTroy James
Light test for kitchen hood exhaust duct. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
Need to know how the walls are being fabricated at the media room. We have insulated ducts in wall cavity insulated at 5.2 r-value.
grease duct light test for second floor kitchen ok
Rough-in5/7/20145/8/20145/8/2014APART
DetailsTroy James
Kitchen studio approve for wrap of ceiling.
Onsite Contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
no inspection at the kitchen studio, ok to insulate ducts at second level area A.
Rough-in4/10/20144/11/20144/11/2014APART
DetailsTroy James
Ceiling inspection, approve for wrap. Inspiration Studio. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to insulate ducts
Rough-in3/31/20144/1/20144/1/2014APART
DetailsTroy James
1st floor ceiling, approval for insulation. Onsite contact: Rob Butler. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to insulate ducts at restroom and dining, ducts not completely installed, partial inspection for duct cover
Conference1/21/20141/22/20141/22/2014ACANC
DetailsTroy James
Approve to cover super column. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
canceled, contractor wants to have conference with dixie
Rough-in12/27/201312/30/201312/30/2013APART
DetailsTroy James
Rough-in for cover. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover ducts in concreted chase/column east side of building that go from the basement to the 3rd level. No fire damper at this time where ducts penetrates the garage ceiling.
Issue PAID IN FULL permit  12/13/2013 DONE
Payment received via Govolutions
Application received  12/13/2013 DONE
This permit was created on the web by Melissa Kaae