First Notice | 1/12/2017 | 1/12/2017 | 7/27/2020 | | DONE |
Troy James
|
|
|
This permit finaled on the web by RM Mechanical
|
Final | 1/12/2017 | 1/13/2017 | 1/12/2017 | A | PASS |
Troy James
|
|
|
Onsite contact: Jason Davidson Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | FAIL |
Troy James
|
|
|
Onsite contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae Need FSD installed at duct penetrating the dust collection room exterior wall.
|
Mec-Aging Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 | | PEND |
Troy James
|
|
|
Talked to contractor. He is going to check into the makers studio to see if final can be done.
|
Rough-in | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Troy James
|
|
|
Valet bathroom Approval for cover Ben Skelton ###-####
Phone #: ###-#### Inspection requested via web by Melissa Kaae ok to cover ceiling, access door required at ceiling to access equipment above
|
Mec-Aging Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 | | PEND |
Troy James
|
|
|
waiting for the air balance for kichen hood first floor and makers studio to be finaled
|
Mec-Aging Inspection | 11/23/2015 | 11/23/2015 | 11/23/2015 | | PEND |
Troy James
|
|
|
wip
|
Final | 8/24/2015 | 8/25/2015 | 8/26/2015 | A | PART |
Troy James
|
|
|
Final for roof only. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae ok fan and duct on roof. roof is complete
|
Final | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | FAIL |
Troy James
|
|
|
On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae Ok temp occupancy. Need some ductwork done on roof and makers studio to be completed.
|
Final | 7/8/2015 | 7/9/2015 | 7/9/2015 | A | FAIL |
Troy James
|
|
|
On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Corrections posted with Ben
|
Rough-in | 6/22/2015 | 6/22/2015 | 6/23/2015 | P | FAIL |
Troy James
|
|
|
Fireplace finalization. On site contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae Still need approval from manufacturer ok for contractor to not pipie the convection pipe to adjacent room.
|
Conference | 6/18/2015 | 6/18/2015 | 6/18/2015 | A | DONE |
Troy James
|
|
|
Conference inspection to fireplace installation compliance. Informed contractor to contact manufacturer for approval. Contractor does not want to install convection duct to interior wall per JUMP requests.
|
Final | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | NR |
Troy James
|
|
|
6th floor kitchen // Ben Phone #: ###-#### no final at this time
|
Rough-in | 6/5/2015 | 6/5/2015 | 6/5/2015 | P | PASS |
Troy James
|
|
|
6th floor kitchen // Ben Phone #: ###-#### ok to cover kitchen area
|
Rough-in | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PART |
Troy James
|
|
|
6th floor kitchen, approval for cover. On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Need to insulate grease duct at hood connection.
|
Rough-in | 2/27/2015 | 2/27/2015 | 2/27/2015 | P | PASS |
Troy James
|
|
|
JUMP Lobby. On site contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae 0k cover 5th floor lobby
|
Rough-in | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PASS |
Troy James
|
|
|
Pioneer lobby, 6th floor. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae Ok to cover ceiling in the pioneer room
|
Rough-in | 2/4/2015 | 2/5/2015 | 2/9/2015 | P | FAIL |
Troy James
|
|
|
6th floor: Bathrooms ; Pioneer Lobby. On site contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae 6th floor ok to cover at bathrooms and lobby. Need to install outside air duct at air handler to the makers studio to the street side as per approved drawings. The daiken ductless units need to have the condensate drain installed and terminate to an approved location.
|
Case Summary (MEC) | | | 1/8/2015 | | DONE |
Christina Prado
|
|
|
|
Rough-in | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Troy James
|
|
|
5th floor bathrooms. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae ok ceiling cover 5th floor restrooms and movement room
|
Rough-in | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Troy James
|
|
|
ok wood ceiling cover at second floor. Ok large duct cover from air handler on roof to inside of buiding at 6th floor.
|
Rough-in | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | CANC |
Troy James
|
|
|
Approval for cover 2nd floor ; 6th floor. Onsite contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae rescheduled inspection for monday morning
|
Rough-in | 11/10/2014 | 11/12/2014 | 11/12/2014 | A | PASS |
Troy James
|
|
|
Ceiling inspection, levels 5 & 6. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover insulate supply runs at 6th kitchen and fsd at 1st floor garage exhaust west side
|
Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Troy James
|
|
|
Re-inspect 5th floor / mech case, Makers Studio. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover chase at makers studio and ok to insulate ducts at 6th floor.
|
Rough-in | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PART |
Troy James
|
|
|
4th floor restroom & re-inspection for Makers Studio mech case for duct collator (also on 4th floor). Onsite contact: Rob Butler. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Ok to cover ceiling at 4th floor restrooms after access door is framed for access to motor at fire damper. Need to remove rubber gasket at dust collector floor sweep and install approved materials.
|
Rough-in | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | FAIL |
Troy James
|
|
|
5th floor HVAC rough-in. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae Need to change the floor sweep with a 45 degree tap. Duct collector to laser room may need explosion relief venting.
|
Rough-in | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | PASS |
Troy James
|
|
|
Mechanical case inspection, 5th floor. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae ok ducts from air handler through shaft to 5th floor and exhaust duct in shaft from 5th to the roof.
|
Rough-in | 9/22/2014 | 9/23/2014 | 9/23/2014 | P | FAIL |
Troy James
|
|
|
Fire smoke dampers 3rd ; 5th floors. Onsite contact: Ben Skelton. Phone #: ###-#### Inspection requested via web by Melissa Kaae need 1/8" per foot of damper gap between damper sleeve and framing.
|
Rough-in | 9/4/2014 | 9/5/2014 | 9/5/2014 | P | PART |
Troy James
|
|
|
2nd floor ceiling cover. Onsite contact: Ben Skelton Phone #: ###-#### Inspection requested via web by Melissa Kaae Ok to cover hard lid ceilings. Contractor will schedule another inspection for tuesday to inspect more ducts being installed for insulation.
|
Rough-in | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PASS |
Troy James
|
|
|
Rough-in for 5th floor maker studio & 2nd floor restrooms. Onsite contact: Rob Butler Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover the spray booth duct with fire wrap and ok the dryer duct at makers studio
|
Rough-in | 8/13/2014 | 8/13/2014 | 8/13/2014 | P | PASS |
Troy James
|
|
|
5th floor // Ben Phone #: ###-#### no inspection on 5th floor. Ok two air handlers at garage tie ins. Ok to cover 1st floor hard lid ceiling.
|
Rough-in | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | FAIL |
Troy James
|
|
|
Rough-In 2nd Floor. Onsite Contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae need 24x24 access doors to fan coil units and two 18x18 access doors under the fire smoke dampers at shaft. Also waiting to here from the structural engineer in regards to the hangers for the fan coil units.
|
Rough-in | 7/29/2014 | 7/30/2014 | 7/31/2014 | P | PASS |
Troy James
|
|
|
Basement & 4th floor restroom. Onsite contact: Ben Skelton Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover restroom and inspiration room.
|
Rough-in | 7/16/2014 | 7/17/2014 | 7/17/2014 | P | FAIL |
Troy James
|
|
|
Grease duct 1st floor & 1st floor restroom. Onsite contact: Ben Skelton Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover grease duct. Access doors are not installed correctly. Need to install per ICC esr report.
|
Rough-in | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | PART |
Troy James
|
|
|
Looked at fsd to shafts at basement. Not complete inspection.
|
Rough-in | 7/7/2014 | 7/8/2014 | 7/8/2014 | P | CANC |
Troy James
|
|
|
4th floor & basement rough-in. Onsite contact Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae reschedule for morning
|
Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PASS |
Troy James
|
|
|
3rd floor media studio, underfloor duct. Approve for insulation cover. Onsite contact: Rob Butler Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to insulate ducts under the media room
|
Rough-in | 6/2/2014 | 6/3/2014 | 6/3/2014 | A | PART |
Troy James
|
|
|
Tom-lite test Phone #: ###-#### ok light test to portion of grease duct pioneer kitchen
|
Rough-in | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PART |
Troy James
|
|
|
Kitchen studio, 2 each, 1st & 2nd floor. Shaft, approve for cover. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover shafts, still need to inspect fsd at basement when ducts enter the shaft
|
Rough-in | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | PART |
Troy James
|
|
|
Multimedia center wall approve for cover. Duct in walls approve for cover. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok ducts in wall at media room, ok to cover shafts west and east at frontier room, still need to inspect fsd where ducts enter shaft from basement, Need to know why vav boxes are not being hung per plans
|
Pressure Test | 5/20/2014 | 5/21/2014 | 5/21/2014 | P | PART |
Chad Schwendiman
|
|
|
MEC-COM/RES INSPECTOR - LIGHT TEST FOR KITCHEN STUDIO HOOD GREASE DUCT IN SHAFT PASS.
|
Rough-in | 5/20/2014 | 5/21/2014 | 5/21/2014 | P | PART |
Chad Schwendiman
|
|
|
MEC-COM/RES INSPECTORN - DUCT APPROVED FOR WRAP NORTH SIDE OF MULTI MEDIA SOFFIT.
|
Pressure Test | 5/13/2014 | 5/14/2014 | 5/14/2014 | A | FAIL |
Troy James
|
|
|
Light test for kitchen hood exhaust duct. Onsite contact: Steve Tow. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Need to know how the walls are being fabricated at the media room. We have insulated ducts in wall cavity insulated at 5.2 r-value. grease duct light test for second floor kitchen ok
|
Rough-in | 5/7/2014 | 5/8/2014 | 5/8/2014 | A | PART |
Troy James
|
|
|
Kitchen studio approve for wrap of ceiling. Onsite Contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae no inspection at the kitchen studio, ok to insulate ducts at second level area A.
|
Rough-in | 4/10/2014 | 4/11/2014 | 4/11/2014 | A | PART |
Troy James
|
|
|
Ceiling inspection, approve for wrap. Inspiration Studio. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to insulate ducts
|
Rough-in | 3/31/2014 | 4/1/2014 | 4/1/2014 | A | PART |
Troy James
|
|
|
1st floor ceiling, approval for insulation. Onsite contact: Rob Butler. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to insulate ducts at restroom and dining, ducts not completely installed, partial inspection for duct cover
|
Conference | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | CANC |
Troy James
|
|
|
Approve to cover super column. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae canceled, contractor wants to have conference with dixie
|
Rough-in | 12/27/2013 | 12/30/2013 | 12/30/2013 | A | PART |
Troy James
|
|
|
Rough-in for cover. Onsite contact: Steve Tow Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover ducts in concreted chase/column east side of building that go from the basement to the 3rd level. No fire damper at this time where ducts penetrates the garage ceiling.
|
Issue PAID IN FULL permit | | | 12/13/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/13/2013 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|