Final | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PASS |
Chad Schwendiman
|
|
|
please call the builder for access Tim Austin ###-#### Phone #: ###-#### >> Inspection requested via web by Jennifer Roy
|
Conference | 9/12/2014 | 9/12/2014 | 9/12/2014 | P | CANC |
Chad Schwendiman
|
|
|
Please call with any questions or concerns. Thank you. Call builder for access ###-####. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy
|
Final | 9/12/2014 | 9/12/2014 | 9/12/2014 | P | FAIL |
Chad Schwendiman
|
|
|
Please call with any questions or concerns. Thank you. Call builder for access ###-####. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy - need to pipe secondary condensate on coil or install a wet switch.
|
Pressure Test | 5/1/2014 | 5/1/2014 | 5/1/2014 | A | PASS |
Chad Schwendiman
|
|
|
Duct blaster test 11:00. Please call with any questions or concerns. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy - 20LB gas pressure pass, 5LB flue test pass
|
Rough-in | 5/1/2014 | 5/1/2014 | 5/1/2014 | A | PASS |
Chad Schwendiman
|
|
|
Duct blaster test 11:00. Please call with any questions or concerns. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy - Duct blast pass, rough in pass
|
Issue PAID IN FULL permit | | | 5/1/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/1/2014 | | DONE |
|
|
|
This permit was created on the web by Jennifer Roy
|