First Notice | 8/11/2014 | 8/11/2014 | 8/2/2017 | | DONE |
Chad Schwendiman
|
|
|
|
Final | 8/8/2014 | 8/11/2014 | 8/11/2014 | A | PASS |
Chad Schwendiman
|
|
|
disconnect on furnace done ducting sealed done ducts terminated done new duct on oven double wall through roof done Thank You for your time. Phone #: ###-#### >> Inspection requested via web by Randy Keuhey
|
Conference | 5/16/2014 | 5/16/2014 | 5/16/2014 | A | DONE |
Chad Schwendiman
|
|
|
Randy ###-#### - CONTRACTOR TO FIX VENT PIPE ON BREAD OVEN, SEAL SUPPLY & RETURN DUCT ON SPLIT SYSTEM, INSTALL SERVICE SHUT OFF SWITCH ON SPLIT SYSTEM, & TERMINATE SUPPLY DUCT IN OFFICE. A/C IS NOT BIENG INSTALLED ON SPLIT SYSTEM AT THIS TIME. WILL PERMIT AT A LATER TIME.
|
Issue PAID IN FULL permit | | | 5/16/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Override - Parcel Holds | | | 5/16/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/16/2014 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 5/16/2014 | | |
|
|
|
|