Final | 4/7/2015 | 4/7/2015 | 4/7/2015 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer
|
Rough-in | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | PASS |
Chad Schwendiman
|
|
|
Mechanical rough in and gas pressure inspection. Phone #: ###-#### Inspection requested via web by Bryan Palmer - 20lb gas pass
|
Pressure Test | 8/28/2014 | 8/28/2014 | 8/28/2014 | P | PASS |
Eric Strole
|
|
|
Radiant floor pressure test. Phone #: ###-#### Inspection requested via web by Bryan Palmer-100 psi test pass
|
Pressure Test | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Chad Schwendiman
|
|
|
Radiant floor pressure test. Phone #: ###-#### >> Inspection requested via web by Bryan Palmer - 100lb pressure test on floor piping
|
Pressure Test | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | PASS |
Chad Schwendiman
|
|
|
Pressure test for geothermal ground-loop. Phone #: ###-#### >> Inspection requested via web by Bryan Palmer - 100LB PRESSURE PASS ON IN GROUND HYDRONIC LOOP.
|
Pressure Test | 7/2/2014 | 7/2/2014 | 7/2/2014 | P | CANC |
Chad Schwendiman
|
|
|
Jason-geo-thermal-loop field test Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/2/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/2/2014 | | DONE |
|
|
|
This permit was created on the web by Bryan Palmer
|