Final | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brad Allison
|
Final | 11/23/2014 | 11/24/2014 | 11/24/2014 | P | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brad Allison-Need 2 foundation vents permanently open in each crawl where there is a furnace. Have air balance reports.
|
Rough-in | 8/12/2014 | 8/12/2014 | 8/12/2014 | P | PASS |
Eric Strole
|
|
|
Inspection requested via web by Brad Allison
|
Rough-in | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | NR |
Bill VanDegrift
|
|
|
Inspection requested via web by Brad Allison 20# gas test ok flues failed and still no ACCA report on site
|
Pressure Test | 8/12/2014 | 8/12/2014 | 8/12/2014 | P | PART |
Bill VanDegrift
|
|
|
Inspection requested via web by Brad Allison 20# gas test ok flues failed
|
Rough-in | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | FAIL |
Chad Schwendiman
|
|
|
>> Inspection requested via web by Brad Allison - Need approved manual j on site with main level and basement floor plans in it. 20lb gas pressure fail. 5lb flue pressure fail
|
Rough-in | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | CANC |
Eric Strole
|
|
|
>> Inspection requested via web by Brad Allison Inspection cancelled from web by: Brad Allison
|
Issue PAID IN FULL permit | | | 7/22/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/22/2014 | | DONE |
|
|
|
This permit was created on the web by Brad Allison
|