Final | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Alan Hauser
|
|
|
|
Pressure Test | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Alan Hauser
|
|
|
2-60# test passed
|
CHANGE STATUS TO (ISS) | | | 10/14/2014 | | DONE |
Candy A. Nichols
|
|
|
as per Alan Hauser-change from final to issue so we can schedule G/P test for Intermountain Gas.
|
Final | 10/3/2014 | 10/3/2014 | 10/3/2014 | P | PASS |
Alan Hauser
|
|
|
|
Pressure Test | 9/24/2014 | 9/25/2014 | 9/25/2014 | A | PASS |
Alan Hauser
|
|
|
2-20# test ok
|
Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Alan Hauser
|
|
|
|
Issue PAID IN FULL permit | | | 8/29/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 8/29/2014 | | |
|
|
|
|
Application received | | | 8/29/2014 | | DONE |
|
|
|
This permit was created on the web by Matthew Benton
|
First Notice | 10/14/2014 | 10/14/2014 | | | |
Alan Hauser
|
|
|
|
First Notice | 10/3/2014 | 10/3/2014 | | | |
Alan Hauser
|
|
|
|