First Notice | 11/3/2015 | 11/3/2015 | 1/22/2016 | | DONE |
Chad Schwendiman
|
|
|
This permit finaled on the web by Dan Flaherty
|
Final | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | PASS |
Chad Schwendiman
|
|
|
Ben/###-####/Final on F, G Phone #: ###-#### Inspection requested via web by Crystal Grant
|
Rough-in | 10/12/2015 | 10/13/2015 | 10/13/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben/###-####/G 1st floor corridors Phone #: ###-#### Inspection requested via web by Crystal Grant okay to cover
|
Conference | 9/28/2015 | 9/28/2015 | 9/28/2015 | A | CANC |
Chad Schwendiman
|
|
|
|
Rough-in | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | PART |
Troy James
|
|
|
Rough In 1st floor G section. Contact Jesse ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty ok to cover first floor ceiling corridor bldg G
|
Rough-in | 7/20/2015 | 7/21/2015 | 7/21/2015 | A | PART |
Chad Schwendiman
|
|
|
Jesse/###-####/ Inspection 4th floor F mechanical. Hard lid Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover hard lid
|
Rough-in | 7/20/2015 | 7/21/2015 | 7/20/2015 | A | CANC |
Eric Strole
|
|
|
###-####/ Inspection 4th floor F mechanical. Hard lid Phone #: ###-#### >> Inspection requested via web by Crystal Grant Inspection cancelled from web by: Crystal Grant
|
Rough-in | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | PART |
Chad Schwendiman
|
|
|
RI on 3rd floor corridors in F ; G. Contact Ben ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - okay to cover hard lids in the corridoor of F wing
|
Rough-in | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben/###-####/4th floor F corridor G 1st 2nd 3rd floor media rooms approve for cover Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover
|
Rough-in | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PART |
Troy James
|
|
|
Ben/###-####/G 1 1st floor soffits Phone #: ###-#### >> Inspection requested via web by Crystal Grant
|
Rough-in | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben ###-####/2nd floor G soffits Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover soffits and hard lids
|
Rough-in | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | PART |
Chad Schwendiman
|
|
|
Ben/###-####/G 3 3rd floor soffits Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover soffits anf hard lids
|
Rough-in | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben ###-####/1st floor F soffits Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover soffits and hard lids
|
Rough-in | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben ###-####/ Soffits F 2nd floor. Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover soffits and hard lids 2nd floor of f wing
|
Rough-in | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PART |
Chad Schwendiman
|
|
|
Ben ###-####/Building F 3rd floor soffits Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover soffits
|
Rough-in | 4/6/2015 | 4/7/2015 | 4/7/2015 | P | PART |
Chad Schwendiman
|
|
|
Ben/###-####/Inspection building F soffits.
Phone #: ###-#### Inspection requested via web by Crystal Grant - 4th floor building f soffits okay to cover.
|
Rough-in | 2/3/2015 | 2/4/2015 | 2/4/2015 | P | PART |
Eric Strole
|
|
|
building F , G. Prerock full building. Ben ###-#### Phone #: ###-#### Inspection requested via web by Crystal Grant-ok to cover ceilings in units only all flrs F&G wing.
|
Issue PAID IN FULL permit | | | 10/23/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/23/2014 | | DONE |
|
|
|
This permit was created on the web by Dan Flaherty
|