Final | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Chad Schwendiman
|
|
|
Sorry about the electric box. I thought that it was installed already. Please call about 1/2 hour before heading there? Phone #: ###-#### Inspection requested via web by Nat Golden
|
Final | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | FAIL |
Chad Schwendiman
|
|
|
Ned Phone #: ###-#### - still need to add power outlet to be able to plug in condensate pump
|
Final | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | FAIL |
Chad Schwendiman
|
|
|
Furnace install final. Phone #: ###-#### Inspection requested via web by Nat Golden - need combustion air vents installed in mech room, need to pipe out secondary condensate or install a wet switch, need to install dryer vent, need outlet for furnace and condensate pump.
|
Pressure Test | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | PASS |
Chad Schwendiman
|
|
|
If we can finalize the furnace install, that would be cool as well. The main purpose is to get pressure test so that the gas company can set the meter. Can you call about 1/2 hour ahead? Phone #: ###-#### Inspection requested via web by Nat Golden - 20lb gas pass. not ready for a final
|
Issue PAID IN FULL permit | | | 3/12/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/12/2015 | | |
|
|
|
|