Final | 8/25/2015 | 8/26/2015 | 8/26/2015 | A | PASS |
Chad Schwendiman
|
|
|
Call Bryan, thank YOU! Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
Final | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PART |
Chad Schwendiman
|
|
|
please call Bryan, thank YOU! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 5th floor okay, parking garage okay. Need to seal roof penetrations, and finish installing mini split systems
|
Rough-in | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Chad Schwendiman
|
|
|
Please call Bryan to meet, 4th floor R/I. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 4th floor okay
|
Final | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | FAIL |
Chad Schwendiman
|
|
|
Final on 4th floor, please call Bryan, Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - need to complete the condensate drains
|
Final | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PART |
Chad Schwendiman
|
|
|
Final for the 3rd floor, please call Bryan. Thank You! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 3rd floor okay
|
Final | 7/29/2015 | 7/29/2015 | 7/29/2015 | P | PART |
Chad Schwendiman
|
|
|
2ND FLOOR, PLEASE CALL BRYAN. THANK YOU. Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 2nd floor west side final okay
|
Rough-in | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PART |
Chad Schwendiman
|
|
|
We need approval to cover, 5th floor, call Bryan. Thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover soffits on 5th floor
|
Rough-in | 7/17/2015 | 7/17/2015 | 7/17/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I to cover in shafts, please call Bryan. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 5th floor shafts okay
|
Rough-in | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I for 5th floor for cover (approve shafts) please call Bryan. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - shafts okay to cover in rooms 506, 508, 510, 514, 515, 516, 518, 520, 522, 525, 544.
|
Final | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | FAIL |
Chad Schwendiman
|
|
|
East and West wing we need a final for the 1st floor lobby and 2nd floor. Please call Bryan. Thank You! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - primary condensate drains need to be traped per manufactures specs, Need wet switch on secondary condensate drains, Need hinged access doors for fire damper accesses.
|
Rough-in | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I for 5th floor. Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover soffits in rooms 503,505,507,509,511,512,513,517,521,524,526,527,528.
|
Rough-in | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I for 5th floor shafts, call Bryan. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - shafts okay in 503, 505, 507, 509, 511,512,513, 517, 521, 524, 526, 527, 528, 532, 534, 536, 537, 540, 541, 543
|
Rough-in | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | PASS |
Troy James
|
|
|
We need a R/I 4th floor west, please call Bryan. Thank YOU! Phone #: ###-#### >> Inspection requested via web by Rhonda Marcum ok cover soffits
|
Rough-in | 6/12/2015 | 6/12/2015 | 6/12/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I 4th floor shafts, call Bryan. Thank YOU! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover shafts
|
Rough-in | 6/10/2015 | 6/10/2015 | 6/10/2015 | P | PART |
Chad Schwendiman
|
|
|
R/I for pre-rock on 5th and 3rd floor, Please call Bryan. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover hard lids and soffits in all rooms on the 3rd floor, okay to cover the bottom of the trusses in all rooms on the 5th floor.
|
Rough-in | 5/26/2015 | 5/27/2015 | 5/27/2015 | A | PART |
Chad Schwendiman
|
|
|
We need a R/I for the second floor, please call Bryan, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover soffits and hard lids in rooms 225, 231, & 233. Smoke fire damper expansion clearances okay on mech. room in middle wing elevator lobby's
|
Rough-in | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PART |
Chad Schwendiman
|
|
|
Please call Bryan, Thank You! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - okay to cover soffits and hard lids on 2nd floor except for rooms 225, 231, & 233. okay to cover bottom of tgi's on 3rd floor and 4th floor. okay to cover ceiling in pool room 1st floor.
|
Issue PAID IN FULL permit | | | 4/28/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/24/2015 | | |
|
|
|
|
First Notice | 8/26/2015 | 8/26/2015 | | | |
Chad Schwendiman
|
|
|
|