Final | 9/25/2015 | 9/25/2015 | 9/25/2015 | P | PASS |
Chad Schwendiman
|
|
|
just in case Phone #: ###-#### Inspection requested via web by Robin Cox
|
Final | 9/24/2015 | 9/25/2015 | 9/25/2015 | A | PEND |
Chad Schwendiman
|
|
|
a final for Friday 9-25-15 in the am. Phone #: ###-#### Inspection requested via web by Robin Cox - Pending air balance report
|
Rough-in | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PASS |
Chad Schwendiman
|
|
|
duct detectors are in. no power. will be able to test at final. need to put ceiling tiles in. thanks Phone #: ###-#### Inspection requested via web by Robin Cox - Okay to cover ceiling. The kitchen equipment isn't all set into place yet, but I called and told Robin that I am concerned about the hood being big enough to over hang the equipment by 6" on all open sides.
|
Final | 9/15/2015 | 9/15/2015 | 9/15/2015 | P | FAIL |
Chad Schwendiman
|
|
|
final for Tuesday 9-15-15 for the afternoon Phone #: ###-#### Inspection requested via web by Robin Cox - 1) supply grills not installed yet. 2) need cooking equipment installed under hood. 3) need a copy of the air balance report. 4) duct smoke detectors not installed 5) flue exhaust hoods not installed on RTU's
|
Rough-in | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Chad Schwendiman
|
|
|
inspect first layer of fire wrap on grease duct Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 8/29/2015 | 8/31/2015 | 8/31/2015 | A | PASS |
Chad Schwendiman
|
|
|
light test for grease duct. please call Robin to let him know what time. ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PART |
Chad Schwendiman
|
|
|
Duct sealer for 8-19-15 morning Phone #: ###-#### Inspection requested via web by Robin Cox - duct seal pass
|
Conference | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | DONE |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Robin Cox - Discussion in regards to clearance from back of hood to wall. with the way the hood was made it will require a 2" stand off in order to have the required clearance to the grease duct
|
Rough-in | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Chad Schwendiman
|
|
|
rough in for the bathrooms Phone #: ###-#### Inspection requested via web by Robin Cox - okay to cover bathroom ceilings
|
Issue PAID IN FULL permit | | | 8/11/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/11/2015 | | DONE |
|
|
|
This permit was created on the web by Robin Cox
|
First Notice | 9/25/2015 | 9/25/2015 | | | |
Chad Schwendiman
|
|
|
|