Final | 3/3/2016 | 3/4/2016 | 3/4/2016 | P | PASS |
Chad Schwendiman
|
|
|
final - builder has revised manual j and air balance - duct blast to be done in late am / early pm. Inspection for late pm if possible. Phone #: ###-#### Inspection requested via web by Brandon Sorensen
|
Final | 3/2/2016 | 3/3/2016 | 3/3/2016 | P | FAIL |
Chad Schwendiman
|
|
|
final - call brandon at the office if any questions Phone #: ###-#### Inspection requested via web by Brandon Sorensen - need air balance report and duct blast report on site
|
Rough-in | 1/5/2016 | 1/7/2016 | 1/7/2016 | A | PART |
Eric Strole
|
|
|
cesar - rough in Phone #: ###-#### Inspection requested via web by Brandon Sorensen-20 lb gas test pass. rough-in pass. Need to have furnace changed on manual-j and add axtra supply and return in crawl to manual-j by final.
|
Issue PAID IN FULL permit | | | 11/3/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/3/2015 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|