First Notice | 9/30/2016 | 9/30/2016 | 1/6/2017 | | DONE |
Chad Schwendiman
|
|
|
|
Print Statement | | | 1/6/2017 | | DONE |
|
|
|
|
Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Chad Schwendiman
|
|
|
Onsite contact: Jeff Rains Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Final | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Call Jeff Rains - Final Inspection Phone #: ###-#### Inspection requested via web by Melissa Kaae - p-traps not installed on roof top units, missing grills in south east room on 1st floor
|
Rough-in | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PART |
Chad Schwendiman
|
|
|
1st floor rough-in cover. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st floor okay to cover grid ceiling except for the room in the south east corner
|
Rough-in | 8/25/2016 | 8/26/2016 | 8/26/2016 | A | CANC |
Chad Schwendiman
|
|
|
4th floor elevator lobby. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover 4th floor elevator lobby
|
Rough-in | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | PASS |
Chad Schwendiman
|
|
|
Cover for 2nd ; 3rd floor elevator lobbies. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover 2nd floor elevator lobby, and confrence room, okay to cover 3rd floor elevator lobby, okay to cover 1st floor living room, and 1st floor ballroom
|
Rough-in | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PART |
Chad Schwendiman
|
|
|
Cover inspection Contact:Jeff Rains Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover 4th floor grid
|
Rough-in | 6/29/2016 | 6/30/2016 | 6/30/2016 | P | PASS |
Ben Livingston
|
|
|
2nd ; 3rd for cover. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 2nd and 3rd floor ok for cover
|
Rough-in | 6/22/2016 | 6/23/2016 | 6/23/2016 | P | PART |
Chad Schwendiman
|
|
|
4th floor conference room. Onsite contact: Jeff Rains Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay no cover soffits in 4th floor confrence room
|
Rough-in | 6/14/2016 | 6/15/2016 | 6/15/2016 | P | PART |
Chad Schwendiman
|
|
|
1st ; 4th floor bathrooms. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - framing around fire dampers in 1st floor bathroom okay, okay to cover 4th floor bathroom ceilings
|
Rough-in | 5/27/2016 | 5/31/2016 | 5/31/2016 | A | PASS |
Ben Livingston
|
|
|
3rd Floor Rough In Inspection Of Rest Room Contact Jeff Rains at ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae- 2nd floor conferance room, 3rd floor restrooms ok to cover.
|
Rough-in | 5/25/2016 | 5/26/2016 | 5/26/2016 | A | PART |
Chad Schwendiman
|
|
|
Various fire dampers. Onsite contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover shafts on 1st and 4th floors. framing around fire dampers okay
|
Conference | 5/18/2016 | 5/18/2016 | 5/18/2016 | P | DONE |
Chad Schwendiman
|
|
|
there was concern over a fireplace install. I went by to look, there hasn't been a fireplace installed yet. I talked to Jeff with RM and he indicated that they have nothing to do with a fireplace being installed.
|
Rough-in | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | PART |
Chad Schwendiman
|
|
|
2nd and 3rd floor rough in inspection above hard lid ceiling. Contact Jeff Rains at ###-####. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover hard lids on the 2nd floor except for conference. okay to cover 3rd floor mens ceiling
|
Conference | 4/7/2016 | 4/7/2016 | 4/7/2016 | P | CANC |
Chad Schwendiman
|
|
|
Phone ###-####
|
Rough-in | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | PART |
Ben Livingston
|
|
|
On site contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae-fire damper clearance 1st 2nd 3rd floor ok to cover, duct 3rd floor ok to insulate
|
Rough-in | 3/2/2016 | 3/8/2016 | 3/8/2016 | A | PART |
Chad Schwendiman
|
|
|
1st ; 2nd floor cover. On site contact: Jeff Rains. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover shaft wall in womens 202, all other fire damper locations still need to have expansion clearances per the manufactors instructions
|
Rough-in | 1/18/2016 | 1/22/2016 | 1/22/2016 | A | PART |
Chad Schwendiman
|
|
|
For cover. On site contact: Jeff Rains Phone #: ###-#### Inspection requested via web by Melissa Kaae - Okay to insulate duct on 2nd, and 3rd floor. okay to cover shafts on 2nd and 3rd floors with out fire dampers. Need to see framing around fire dampers per manufactures instructions before covering.
|
Issue PAID IN FULL permit | | | 11/12/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/12/2015 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|