Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberMEC16-00048
StatusFinaled
Name TVR INC
Site Address 400 S BROADWAY AVE
Project NameWGP1 - St Luke's TI
Customer Number 
ePlanReviewNo
Description
Addition: Provide and Install 231 each TraneVAV Double Duct Terminal Units with Air-Fi Controllers
Provide and install 14 each Trane VAV Single Duct Terminal Units with Air-Fi Controllers
Provide and Install 9 each Ductless Split systems
Provide and Install T
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/20/20166/21/20166/21/2016APASS
DetailsChad Schwendiman
final - am Phone #: ###-#### Inspection requested via web by Brandon Sorensen
Rough-in6/13/20166/14/20166/14/2016APART
DetailsChad Schwendiman
first floor cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 1st floor ceiling okay to cover
Rough-in5/31/20165/31/20165/31/2016PPART
DetailsChad Schwendiman
plenum wrap for basement Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover basement coridoor ceilings
Final5/25/20165/26/20165/26/2016APART
DetailsChad Schwendiman
final for 4th and 5th floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 5th, 4th, and 3rd floor okay
Final5/25/20165/25/20165/25/2016PCANC
DetailsChad Schwendiman
final for 4th and 5th floor Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen Inspection cancelled from web by: Brandon Sorensen
Final5/19/20165/20/20165/20/2016APART
DetailsChad Schwendiman
Chad - 6th floor final and cover for basement Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover rooms in basement, need to complete protection of nonrated wires in corridoor in the basement. 6th floor okay
Rough-in5/4/20165/5/20165/5/2016APART
DetailsChad Schwendiman
cover for 2nd floor, partial hard lid for basement and 1st floor Phone #: ###-#### Inspection requested via web by Brandon - okay to cover gris ceiling on the 2nd floor, okay to cover 1st floor hard lids in corridors, okay to cover new bathroom ceiling in the basement
Rough-in4/26/20164/27/20164/27/2016APASS
DetailsChad Schwendiman
cover for 3rd floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover grid ceilings
Rough-in4/18/20164/19/20164/19/2016APART
DetailsChad Schwendiman
4th Floor Cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover grid ceilings in the 4th floor, 1st floor duct okay
Conference4/5/20164/6/20164/6/2016ADONE
DetailsChad Schwendiman
Basement Plenum Question Phone #: ###-#### Inspection requested via web by Brandon Sorensen - conference to discuss unprotected non plenum rated material in the return plenum in the basement. The non rated material will need to be protected to meet the current codes.
Rough-in4/1/20164/4/20164/4/2016APASS
DetailsBen Livingston
5th floor cover, 2nd floor hard lid Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 2nd floor hard lids, 5th floor cover
Rough-in3/21/20163/22/20163/22/2016APASS
DetailsBen Livingston
2nd floor hard lid Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 3rd floor ok to cover hard lids,, 6th floor grid ok to cover
Rough-in3/7/20163/8/20163/8/2016APART
DetailsChad Schwendiman
4th floor hard lid - late am Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 4th floor hard lids okay to cover
Rough-in3/7/20163/8/20163/7/2016ACANC
DetailsChad Schwendiman
4th floor hard lid inspection - early am Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen Inspection cancelled from web by: Brandon Sorensen
Rough-in2/17/20162/18/20162/18/2016APASS
DetailsBen Livingston
6th Floor hard lid - am Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 6th floor corridors approved for cover
Rough-in2/9/20162/10/20162/10/2016APART
DetailsChad Schwendiman
6th Floor - rough in Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 2 corridoor vavs okay on 6th floor.
Conference1/26/20161/27/20161/27/2016ADONE
DetailsChad Schwendiman
call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - prelimanary job walk with Cary. Gave the okay to insulate duct once it's sealed. I expressed the need for the install to be per the engineered drawings.
Issue PAID IN FULL permit  1/5/2016 DONE
Payment received via Govolutions
Application received  1/5/2016 DONE
This permit was created on the web by Brandon Sorensen
First Notice6/21/20166/21/2016   
DetailsChad Schwendiman