First Notice | | 11/30/2017 | 11/30/2017 | | DONE |
|
|
|
final value per GC for Debest (mechanical and plumbing permits together is $215,125). see Plm16-00108 for additional fees.
|
First Notice | 7/17/2017 | 7/17/2017 | 7/18/2017 | | DONE |
Brian Scoles
|
|
|
This permit finaled on the web by Stacia Haumann
|
Final | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Brian Scoles
|
|
|
IF QUESTIONS CALL JERRY @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- final on library per Bill V ok per phone conversation- valve that was blocked for access has been addressed and fixed per phone call to Jerry
|
Final | 4/28/2017 | 5/2/2017 | 5/2/2017 | A | PART |
Brian Scoles
|
|
|
10 AM - If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- temp occupancy ok- need to look at valve that has access issue per pre occupancy report/ air balance report
|
Final | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | CANC |
Brian Scoles
|
|
|
If questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- no commisioning report onsite- general contractor scheduling meeting for next week sometime
|
Rough-in | 3/24/2017 | 3/24/2017 | 3/24/2017 | A | PASS |
Brian Scoles
|
|
|
walked job with Jerry- whole building ok for cover- missing a few stickers and pipe insulation- Jerry will take care of it per conversation
|
Final | 3/23/2017 | 3/24/2017 | 3/24/2017 | A | CANC |
Brian Scoles
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- this should have been rough in for cover inspection
|
Pressure Test | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | PASS |
Brian Scoles
|
|
|
Pressure Test - Hydronic piping - Mechanical room. If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- mech room press test pass- ok to insuate pipe- all building hydronics complete- need labels on all piping before final
|
Pressure Test | 2/1/2017 | 2/1/2017 | 2/1/2017 | P | PASS |
Brian Scoles
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- 60lb gas x2 pass from meter to mech room and mech room to fireplace
|
Pressure Test | 11/9/2016 | 11/10/2016 | 11/10/2016 | A | PASS |
Brian Scoles
|
|
|
Hydronic Pressure test. If questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- 100lb hydronic pass eastside of building
|
Pressure Test | 10/21/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Brian Scoles
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- 20lb gas pass westside from fireplace to mech room
|
Pressure Test | 10/13/2016 | 10/14/2016 | 10/14/2016 | A | PASS |
Brian Scoles
|
|
|
Mechanical Hydronic pressure test. if questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- 100lb hydronic west side overhead pass- ok to insulate
|
Pressure Test | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PASS |
Brian Scoles
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- (2) 100lb hydronic press test pass- grid line 4 in wall
|
Mec-Aging Inspection | 8/4/2016 | 8/4/2016 | 8/4/2016 | | CANC |
Brian Scoles
|
|
|
work in progress
|
Pressure Test | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | PASS |
Chad Schwendiman
|
|
|
U/G Hydronic Line Pressure Test. If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann - 100lb hydronics pass on underground across the middle of the building
|
Issue PAID IN FULL permit | | | 1/12/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/12/2016 | | DONE |
|
|
|
This permit was created on the web by Stacia Haumann
|