Final | 2/9/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Chad Schwendiman
|
|
|
revised as per bldg inspector Phone #: ###-#### Inspection requested via web by Raul Castanon
|
Rough-in | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon - Not installed per approved drawings. Need to submit new drawings for approval or install per the approved drawings
|
Issue PAID IN FULL permit | | | 2/4/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/4/2016 | | |
|
|
|
|
Application received | | | 2/4/2016 | | DONE |
|
|
|
This permit was created on the web by Raul Castanon
|
First Notice | 2/9/2016 | 2/9/2016 | | | |
Chad Schwendiman
|
|
|
|