First Notice | 6/15/2016 | 6/15/2016 | 8/22/2016 | | DONE |
Troy James
|
|
|
This permit finaled on the web by Shelia Gibson
|
Rough-in | 6/14/2016 | 6/15/2016 | 6/15/2016 | P | PASS |
Troy James
|
|
|
pre-final mechanical inspection so he can provide occupancy by Thursday. Phone #: ###-#### Inspection requested via web by Shelia Gibson
|
Final | 6/15/2016 | 6/15/2016 | 6/15/2016 | P | PASS |
Troy James
|
|
|
pre-final mechanical inspection so he can provide occupancy by Thursday. Phone #: ###-#### Inspection requested via web by Shelia Gibson
|
Rough-in | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Troy James
|
|
|
|
Rough-in | 2/29/2016 | 3/1/2016 | 3/1/2016 | P | FAIL |
Troy James
|
|
|
Phone #: ###-#### Inspection requested via web by Shelia Gibson Need to verify pvc pipe will be approved for open plenum in office area
|
Issue PAID IN FULL permit | | | 2/29/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/29/2016 | | DONE |
|
|
|
This permit was created on the web by Shelia Gibson
|