First Notice | 10/28/2016 | 10/28/2016 | 11/16/2016 | | DONE |
Chad Schwendiman
|
|
|
This permit finaled on the web by william kerwin
|
Final | 10/28/2016 | 10/28/2016 | 10/28/2016 | A | PASS |
Chad Schwendiman
|
|
|
|
Final | 8/31/2016 | 8/31/2016 | 8/31/2016 | A | PART |
Chad Schwendiman
|
|
|
Bj 5730755 Inspection requested via web by william kerwin - Temporary occupancy okay. all but unit 101 okay. condensate not complete in unit 101
|
Final | 8/30/2016 | 8/30/2016 | 8/30/2016 | P | PART |
Chad Schwendiman
|
|
|
bj ###-#### Inspection requested via web by william kerwin - all units okay except for 206, and 101
|
Rough-in | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | CANC |
Chad Schwendiman
|
|
|
Drop ceilimgs Inspection requested via web by william kerwin - this is the wrong permit
|
Rough-in | 6/7/2016 | 6/7/2016 | 6/7/2016 | A | PART |
Chad Schwendiman
|
|
|
Drop ceilings Inspection requested via web by william kerwin - okay to cover drop ceilings in the bathrooms
|
Rough-in | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PART |
Chad Schwendiman
|
|
|
angle inspection Inspection requested via web by william kerwin angles on fire dampers okay
|
Rough-in | 5/17/2016 | 5/17/2016 | 5/17/2016 | A | FAIL |
Chad Schwendiman
|
|
|
3rd floor rough. Units and corridor Inspection requested via web by william kerwin - There is no 3rd floor on this bldg. the wrong permit was called in. Need to schedule the right permit
|
Rough-in | 4/8/2016 | 4/8/2016 | 4/8/2016 | A | PASS |
Chad Schwendiman
|
|
|
Late am please thanks Inspection requested via web by william kerwin
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/28/2016 | | DONE |
|
|
|
This permit was created on the web by william kerwin
|