Final | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Ben Livingston
|
|
|
Inspection requested via web by 4 Seasons
|
Final | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | FAIL |
Ben Livingston
|
|
|
Please do a final re-inspection. The line sets have been wrapped with the new line set tape. Inspection requested via web by 4 Seasons need to finish covering all linesets
|
Final | 9/26/2016 | 9/27/2016 | 9/27/2016 | A | FAIL |
Ben Livingston
|
|
|
Inspection requested via web by 4 Seasons armaflex needs uv protection by an approved product
|
Rough-in | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Ben Livingston
|
|
|
Please do a rough-in Re inspection and a water heater flue vent pressure test. Call James at ###-#### with any questions. Thanks Inspection requested via web by 4 Seasons- 5lb flue, rough in
|
Rough-in | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | FAIL |
Ben Livingston
|
|
|
Please do a rough-in and pressure witness. Manual J is nailed to the wall studs by the stairs. All gastite fittings have been redone. Call James at ###-#### with any questions, thanks. Inspection requested via web by 4 Seasons 6" fresh air needs to be sidwall, cannot come off roof, primary condensate iant complete
|
Pressure Test | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | PASS |
Ben Livingston
|
|
|
Please do a rough-in and pressure witness. Manual J is nailed to the wall studs by the stairs. All gastite fittings have been redone. Call James at ###-#### with any questions, thanks. Inspection requested via web by 4 Seasons - 60 lb gas
|
Rough-in | 4/15/2016 | 4/15/2016 | 4/15/2016 | P | FAIL |
Ben Livingston
|
|
|
Please do a rough-in and pressure witness. Inspection requested via web by 4 Seasons- need approved manual j on site, flash shield gas pipe needs to be installed per manufactures instructions.
|
Issue PAID IN FULL permit | | | 4/6/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/6/2016 | | DONE |
|
|
|
This permit was created on the web by 4 Seasons
|