Final | 6/9/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Ben Livingston
|
|
|
Balance report is in your in box Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 6/1/2016 | 6/1/2016 | 6/1/2016 | A | PART |
Ben Livingston
|
|
|
ceiling inspection to drop yile Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 5/27/2016 | 5/27/2016 | 5/27/2016 | P | PASS |
Ben Livingston
|
|
|
second layer of fire wrap to be inspected Phone #: ###-#### Inspection requested via web by Robin Cox- fire wrap ok,, ok to drop tile
|
Rough-in | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Ben Livingston
|
|
|
1st layer grease duct wrap inspection Phone #: ###-#### Inspection requested via web by Robin Cox- 1st layer ok to continue..
|
Rough-in | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Ben Livingston
|
|
|
cover wrap for insulation on supply and return ducts, and light test. requested by mike ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox- ok to ins. grease duct ok to wrap
|
Rough-in | 5/16/2016 | 5/16/2016 | 5/16/2016 | P | PASS |
Ben Livingston
|
|
|
inspect grease duct. mike is on site ###-#### Smash burger Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PASS |
Ben Livingston
|
|
|
duct seal inspection for Chipolte Phone #: ###-#### Inspection requested via web by Robin Cox duct seal
|
Rough-in | 5/10/2016 | 5/10/2016 | 5/10/2016 | P | PART |
Ben Livingston
|
|
|
cover for bathrooms Phone #: ###-#### Inspection requested via web by Robin Cox- ok to cover bathrooms
|
Issue PAID IN FULL permit | | | 4/11/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 4/11/2016 | | |
|
|
|
|
Application received | | | 4/11/2016 | | DONE |
|
|
|
This permit was created on the web by Robin Cox
|
First Notice | 6/9/2016 | 6/9/2016 | | | |
Ben Livingston
|
|
|
|