First Notice | 9/21/2016 | 9/21/2016 | 7/13/2017 | | DONE |
Chad Schwendiman
|
|
|
This permit finaled on the web by Dan Flaherty
|
Print Statement | | | 4/20/2017 | | DONE |
|
|
|
sent 1st late final value
|
Print Statement | | | 1/18/2017 | | DONE |
|
|
|
|
Print Statement | | | 11/22/2016 | | DONE |
|
|
|
|
Final | 9/21/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Chad Schwendiman
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Crystal Grant
|
Final | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PART |
Chad Schwendiman
|
|
|
Antonio/final inspection Phone #: ###-#### Inspection requested via web by Crystal Grant - Need air balance report for class 1 hood. everthing else is okay
|
Rough-in | 8/10/2016 | 8/11/2016 | 8/11/2016 | A | NR |
Chad Schwendiman
|
|
|
Rough in for cover in Deli. Contact Antonio ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | PART |
Chad Schwendiman
|
|
|
Brian ###-####/ Pharmacy rough in Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover pharmacy area
|
Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PART |
Chad Schwendiman
|
|
|
Light test Grease duct 1:pm at TML shop - light test on grease duct pass
|
Rough-in | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PART |
Chad Schwendiman
|
|
|
Antonio/cover inspection for coin room/###-#### Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to cover teller and coin room
|
Rough-in | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | PART |
Chad Schwendiman
|
|
|
Antonio/###-####/rough in for teller and coin room. Phone #: ###-#### Inspection requested via web by Crystal Grant - okay to insulate duct
|
Issue PAID IN FULL permit | | | 5/5/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 5/4/2016 | | |
|
|
|
|
Application received | | | 5/4/2016 | | DONE |
|
|
|
This permit was created on the web by Crystal Grant
|