Final | 1/27/2017 | 1/27/2017 | 1/27/2017 | P | PASS |
Ben Livingston
|
|
|
Call kevin 20 min ahead to open door Thanks Phone #: ###-#### Inspection requested via web by Manuel Canto
|
Rough-in | 10/10/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Ben Livingston
|
|
|
Job will be ready around 9:30 Call Manny 20 min ahead Thanks Phone #: ###-#### Inspection requested via web by Manuel Canto 20 lb gas
|
Rough-in | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | NR |
Ben Livingston
|
|
|
Call me Manny 20 min ahead to meet inspector at the jobsite,also we need to inspect pressure test so I can fire furnace back up Phone #: ###-#### Inspection requested via web by Manuel Canto
|
Rough-in | 8/12/2016 | 8/12/2016 | 8/12/2016 | A | PART |
Ben Livingston
|
|
|
This inspection is a partial to inspect all bath fans for all bathrooms wich are ran thru floor joists from upper level...so framers can close floor on the upper level and continue framing...thanks Call chet 20 min advance so he can meet inspector there and open door for him there''s no people at this house. Phone #: ###-#### Inspection requested via web by Manuel Canto- 5 bath fans, 4 floor vents on 2nd floor ok for cover
|
Issue PAID IN FULL permit | | | 7/25/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/25/2016 | | DONE |
|
|
|
This permit was created on the web by Manuel Canto
|