Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberMEC16-03376
StatusFinaled
Name RM MECHANICAL
Site Address 777 W MAIN ST Unit: 115
Project Name 
Customer NumberD16-007
ePlanReviewNo
Description
Alteration: Provide and install complete Tenant Improvement VRF system, including controls and ductwork. Install exhaust fan and associated ductwork and controls.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice10/13/201610/13/20167/27/2020 DONE
DetailsChad Schwendiman
This permit finaled on the web by RM Mechanical
Final10/13/201610/13/201610/13/2016PPASS
DetailsChad Schwendiman
Final Mechanical Inspection - Please contact Jim Brown. TAB Report to be emailed to Chad S. and Bill V. Phone #: ###-#### Inspection requested via web by Melissa Kaae
Rough-in9/23/20169/26/20169/26/2016PPASS
DetailsChad Schwendiman
Rough-in cover. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Okay to cover celings
Rough-in9/23/20169/26/20169/23/2016ACANC
DetailsChad Schwendiman
Rough-in cover. Onsite contact: Jim Brown. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
Rough-in9/21/20169/22/20169/22/2016APASS
DetailsChad Schwendiman
Light test inspection for exhaust fan connection on the roof. Please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - light test pass for grease duct on the roof
Rough-in9/21/20169/21/20169/21/2016PFAIL
DetailsChad Schwendiman
The venting for the boilers installed in the VRT space in the basement exceeds the manufactures total lenth allowed, the manufacture also calls out for the vent to slope up at a 1/4" per foot from the boilers to the termination location
Rough-in9/15/20169/15/20169/15/2016PPASS
DetailsChad Schwendiman
2nd Layer Grease wrap inspection, please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer of fire wrap pass
Rough-in9/9/20169/13/20169/13/2016APART
DetailsChad Schwendiman
Grease duct 1st layer grease wrap inspection 1st Floor, requesting to be first inspection of the day if possible, thanks. Please contact Jim Brown.
Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer of fire wrap okay
Rough-in9/9/20169/12/20169/12/2016APART
DetailsChad Schwendiman
Grease duct light test inspection 1st Floor, requesting to be first inspection of the day if possible, thanks. Please contact Jim Brown.
Phone #: ###-#### Inspection requested via web by Melissa Kaae - light test pass from existing grease duct stubbed into the space to the hood connection
Conference8/29/20168/30/20168/30/2016ADONE
DetailsChad Schwendiman
On roof to look at final location of exhaust fan. Onsite contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - The location of the fan is acceptable
Issue PAID IN FULL permit  7/27/2016 DONE
Payment received via Govolutions
Owner Supplied Equipment  7/27/2016  
Application received  7/27/2016 DONE
This permit was created on the web by Melissa Kaae