Final | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Troy James
|
|
|
|
Mec-Aging Inspection | 2/13/2018 | 2/13/2018 | 2/13/2018 | | DONE |
Troy James
|
|
|
|
Final | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PART |
Troy James
|
|
|
okay final building except for air handler 5 and 6.
|
Rough-in | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | CANC |
Troy James
|
|
|
|
Rough-in | 8/3/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PASS |
Troy James
|
|
|
weekly inspection east side level 20 and 30
|
Rough-in | 7/20/2017 | 7/20/2017 | 7/20/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 7/13/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Troy James
|
|
|
Weekly inspection, looked at air handlers on roof and exhaust.
|
Rough-in | 7/6/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Troy James
|
|
|
|
Rough-in | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PART |
Troy James
|
|
|
Need to fix fire damper flange at return in lobby. Fire stop fire damper flange on the exhaust duct and secure flange above to framing membrane. Walked west side of building all three levels.
|
Rough-in | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | PASS |
Troy James
|
|
|
fire damper inspection Ok framing and expansion gap inspection for fire dampers west side.
|
Rough-in | 6/22/2017 | 6/22/2017 | 6/22/2017 | P | PASS |
Troy James
|
|
|
Walked the jobsite and discussed items that need to be completed for TCO
|
Rough-in | 6/15/2017 | 6/15/2017 | 6/15/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | PASS |
Troy James
|
|
|
weekly inspection. Walked east and west level 20
|
Rough-in | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PASS |
Troy James
|
|
|
Inspected fire damper locations. Inspected east side chemical room areas. Tea cup bldg.
|
Rough-in | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | PASS |
Troy James
|
|
|
Inspected level 20 and 30, intertestial
|
Rough-in | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | PASS |
Troy James
|
|
|
Met contractor on site to go over drawings for locations of fire dampers.
|
Rough-in | 4/6/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 3/23/2017 | 3/23/2017 | 3/23/2017 | P | PASS |
Troy James
|
|
|
Marked set of plans for completion.
|
Rough-in | 3/16/2017 | 3/16/2017 | 3/17/2017 | P | CANC |
Troy James
|
|
|
|
Rough-in | 3/9/2017 | 3/9/2017 | 3/9/2017 | P | PASS |
Troy James
|
|
|
weekly inspection performed
|
Rough-in | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Troy James
|
|
|
weekly inspection of work in progress
|
Rough-in | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PASS |
Troy James
|
|
|
weekly inspection
|
Rough-in | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PASS |
Troy James
|
|
|
Performed my weekly inspection. two weeks from today I informed YMC to pull permit for work performed. At that time I performed my first inspection.
|
Issue PAID IN FULL permit | | | 2/8/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/2/2017 | | |
|
|
|
|
Application received | | | 2/2/2017 | | DONE |
|
|
|
This permit was created on the web by Xenon Long
|
First Notice | 2/13/2018 | 2/13/2018 | | | |
Troy James
|
|
|
|