Final | 3/31/2017 | 3/31/2017 | 3/31/2017 | A | PASS |
Chad Schwendiman
|
|
|
Air balance report to be emailed to Chad. Phone #: ###-#### Inspection requested via web by Steve Torgerson
|
Final | 3/30/2017 | 3/30/2017 | 3/30/2017 | P | NR |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Torgerson - need air balance report
|
Final | 3/28/2017 | 3/28/2017 | 3/28/2017 | A | NR |
Ben Livingston
|
|
|
inspect to cover inside of building. Still waiting parts for rooftop equipment. Phone #: ###-#### Inspection requested via web by Steve Torgerson
|
Rough-in | 3/28/2017 | 3/28/2017 | 3/28/2017 | A | PASS |
Ben Livingston
|
|
|
inspect to cover inside of building. Still waiting parts for rooftop equipment. Phone #: ###-#### Inspection requested via web by Steve Torgerson above grid okay
|
Rough-in | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Chad Schwendiman
|
|
|
grease duct light test pass
|
Rough-in | 3/22/2017 | 3/22/2017 | 3/22/2017 | A | FAIL |
Chad Schwendiman
|
|
|
Grease Duct light test. Please schedule as early as possible. Call Steve Torgerson @ ###-#### to confirm meeting Phone #: ###-#### Inspection requested via web by Steve Torgerson - need to fix holes in grease duct
|
Rough-in | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PART |
Chad Schwendiman
|
|
|
light test grease duct Phone #: ###-#### Inspection requested via web by Steve Torgerson - light test pass on 5' drop from curb, and 3' piece with a 45 on top of hood
|
Rough-in | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Chad Schwendiman
|
|
|
Duct seal inspection. Phone #: ###-#### Inspection requested via web by Steve Torgerson - okay to insulate ductwork
|
Issue PAID IN FULL permit | | | 3/2/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 3/2/2017 | | |
|
|
|
|
Application received | | | 3/2/2017 | | DONE |
|
|
|
This permit was created on the web by Steve Torgerson
|
First Notice | 3/31/2017 | 3/31/2017 | | | |
Chad Schwendiman
|
|
|
|