Final | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | PASS |
Ben Livingston
|
|
|
WILL Phone #: ###-####
|
Final | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | FAIL |
Ben Livingston
|
|
|
Will Phone #: ###-#### still need corrections
|
Final | 7/31/2017 | 8/1/2017 | 8/1/2017 | A | FAIL |
Ben Livingston
|
|
|
Will Phone #: ###-#### need to fix angle on 4th floor, firedampers need to be at lid
|
Rough-in | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PASS |
Ben Livingston
|
|
|
will - roof Phone #: ###-#### 1st floor soffits okay
|
Rough-in | 5/22/2017 | 5/22/2017 | 5/22/2017 | P | PASS |
Ben Livingston
|
|
|
2nd floor // Will Phone #: ###-#### 2nd floor okay
|
Rough-in | 5/18/2017 | 5/19/2017 | 5/19/2017 | A | FAIL |
Ben Livingston
|
|
|
Ed Phone #: ###-#### 2nd floor needs roughin sleaves for fire dampers in transfer duct
|
Rough-in | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Ben Livingston
|
|
|
Will-4th floor Phone #: ###-#### 4th floor balconies okay
|
Rough-in | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PASS |
Ben Livingston
|
|
|
Will-3rd floor Phone #: ###-#### 3rd floor okay
|
Rough-in | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PART |
Ben Livingston
|
|
|
4th floor interior cover// Will ###-#### interior okay, balconies not ready
|
Rough-in | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | PASS |
Ben Livingston
|
|
|
Dillon-pre rock cover up re inspect-1st, 2nd & 3rd floor Phone #: ###-#### 1st-3rd floor prerock okay
|
Rough-in | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | FAIL |
Ben Livingston
|
|
|
Dillon Phone #: ###-#### exhaust duct needs more hangers, 2nd and 3rd floor exhaustconnections need to be finished
|
Issue PAID IN FULL permit | | | 4/3/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/3/2017 | | DONE |
|
|
|
This permit was created on the web by Brandon Lund
|
First Notice | 8/4/2017 | 8/4/2017 | | | |
Ben Livingston
|
|
|
|