Final | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PASS |
Jack Reynolds
|
|
|
5lb flue pressure test- flue test ok- furnace ac coil ok
|
Final | 9/5/2018 | 9/6/2018 | 9/6/2018 | P | FAIL |
Jack Reynolds
|
|
|
Jonny Phone #: ###-####- 5lb flue pressure test fail gauge was at zero
|
Final | 8/16/2018 | 8/17/2018 | 8/17/2018 | P | FAIL |
Jack Reynolds
|
|
|
Johnny Phone #: ###-#### - duct work in basment needs to be sealed- line set in basement needs supports/ strapped- need to witness a 5lb flue test on furnace- A/C fuse size has one fuse that is too large- line set insulation needs UV protection- lineset needs insulation where it penetrates the building and the penetrations need to be sealed
|
Mec-Aging Inspection | 8/15/2018 | 8/15/2018 | 8/15/2018 | | DONE |
Jack Reynolds
|
|
|
called contractor to schedule inspection
|
Mec-Aging Inspection | 5/16/2018 | 5/16/2018 | 5/16/2018 | | CANC |
Chad Schwendiman
|
|
|
|
Pressure Test | 9/27/2017 | 9/27/2017 | 9/27/2017 | P | PASS |
Chad Schwendiman
|
|
|
Johnny Phone #: ###-#### - 20lb gas pass
|
(F) Reprint permit | | | 9/22/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/7/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/7/2017 | | DONE |
|
|
|
This permit was created on the web by johnny frank
|
First Notice | 9/7/2018 | 9/7/2018 | | | |
Jack Reynolds
|
|
|
|