First Notice | 3/29/2018 | 3/29/2018 | 7/27/2020 | | DONE |
Brian Scoles
|
|
|
This permit finaled on the web by RM Mechanical
|
Print Statement | | | 10/23/2018 | | DONE |
|
|
|
|
Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Brian Scoles
|
|
|
final ok- commissioning report ok
|
Final | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PART |
Brian Scoles
|
|
|
Site contact: Rick Manske fire safety administration building. Phone #: ###-#### Inspection requested via web by Melissa Kaae- ceiling ok to install ceiling tiles- duct work flex all good- need air balance report for final inspection
|
Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PART |
Alan Hauser
|
|
|
hard ceiling areas ok in admin. bldg. and office and bathroom duct ok in training bldg.
|
Rough-in | 9/29/2017 | 10/2/2017 | 10/2/2017 | A | PART |
Alan Hauser
|
|
|
Rough-in inspection of the Administration Building duct work and associated equipment. Contact person: Jeff Rains. Phone #: ###-#### all duct sealed and ready for insulation
|
Issue PAID IN FULL permit | | | 9/19/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/19/2017 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|