Final | 1/17/2018 | 1/17/2018 | 1/17/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz- final on both units ok
|
Final | 1/15/2018 | 1/16/2018 | 1/16/2018 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz- both units need air balance redone below 80%
|
Final | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | CANC |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz- will reschedule per phone call
|
Conference | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Brian Scoles
|
|
|
Doing Duct Blast 1/10/18 @ 9:00 am Phone #: ###-#### Inspection requested via web by Konrad Swartz- duct blast test pass both units
|
Rough-in | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Chad Schwendiman
|
|
|
Inspection requested via web by Konrad Swartz
|
Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz - Need to fur out walls for dryer ducts in both units, Need nail plates on condensate lines both units
|
Issue PAID IN FULL permit | | | 10/20/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/20/2017 | | DONE |
|
|
|
This permit was created on the web by Konrad Swartz
|