Final | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Brian Scoles
|
|
|
Field Super : Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney- final ok
|
Rough-in | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PASS |
Brian Scoles
|
|
|
Field Super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney- R/I ok- need 1' clearance on b vent at water heater location to sheetrock at final
|
Pressure Test | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PASS |
Brian Scoles
|
|
|
Field Super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney- 20lb gas pass
|
Pressure Test | 12/4/2017 | 12/5/2017 | 12/5/2017 | A | PASS |
Chad Schwendiman
|
|
|
Field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney - 20lb gas
|
Rough-in | 12/4/2017 | 12/5/2017 | 12/5/2017 | A | FAIL |
Chad Schwendiman
|
|
|
Field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney - Crawl not complete
|
Issue PAID IN FULL permit | | | 10/26/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/26/2017 | | |
|
|
|
|
Miscellaneous action | | | 10/26/2017 | | DONE |
|
|
|
customers were having problems with the internet and so i helped them get the permit ready
|