Final | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Jason Baxter
|
Final | 4/16/2018 | 4/17/2018 | 4/17/2018 | A | FAIL |
Chad Schwendiman
|
|
|
Looked at dryer. Only 6 in. piece of pipe and an elbow. If you need to get into the building the code is 5550. Phone #: ###-#### Inspection requested via web by Jason Baxter - Need 1" clearance to combustables from b-vent where it passes through sheetrock ceiling
|
Telephone call | | | 4/16/2018 | | DONE |
|
|
|
per phone call from Brenda with Comfort Htg. add dryer vent to permit
|
Final | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | NR |
Bill VanDegrift
|
|
|
Been waiting for proper breaker size for AC to final out. Phone #: ###-#### Inspection requested via web by Brenda Baxter not ready, still needs a permit for the dryer vent.
|
Rough-in | 2/2/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Brian Scoles
|
|
|
R/I ok- dryer vent being installed by different contractor will need permit pulled for it by final
|
Rough-in | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PART |
Brian Scoles
|
|
|
Jason Phone #: ###-####- contractor will talk to homeowner about adding dryer vent to permit- need 3 screws in flue- need 2nd drain ran out or wet switch installed- need uv protection on armorflex outside at AC- AC needs right size breaker installed electricans to change- Rough in OK excluding dryer exhaust
|
Final | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | CANC |
Brian Scoles
|
|
|
Jason Phone #: ###-####
|
Application received | | | 1/22/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/22/2018 | | DONE |
|
|
|
|