Final | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Brian Scoles
|
|
|
gas piping final ok
|
Final | 7/27/2018 | 7/30/2018 | 7/30/2018 | P | NR |
Brian Scoles
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- still working on misc gas piping
|
Pressure Test | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PASS |
Brian Scoles
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 20lb gas pass from roof to cook line- need all piping secured on roof- need drip legs between gas shut off and appliances-
|
Pressure Test | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | NR |
Brian Scoles
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- not holding pressure- will inspect this afternoon per conversation with Mel
|
Final | 7/26/2018 | 7/27/2018 | 7/27/2018 | P | CANC |
Brian Scoles
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- there needs a low pressure gas test for cooking line that never got called in for- its not holding pressure- will reschedule per text with Chris for next week
|
Pressure Test | 4/23/2018 | 4/23/2018 | 4/23/2018 | A | PASS |
Brian Scoles
|
|
|
60lb gas pass- from meter bar location to roof and one 3/4 down the wall
|
Pressure Test | 4/19/2018 | 4/20/2018 | 4/20/2018 | P | FAIL |
Brian Scoles
|
|
|
MEL IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- need pvc sleeve at penetration from meter thru wall- need to support 3/4" gas line in wall- talked to mel about issues and will need retested
|
Issue PAID IN FULL permit | | | 1/24/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/24/2018 | | DONE |
|
|
|
This permit was created on the web by BECCA DUMMER
|
First Notice | 8/10/2018 | 8/10/2018 | | | |
Brian Scoles
|
|
|
|