Final | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | PASS |
Brian Scoles
|
|
|
Bj 5730755 Inspection requested via web by william kerwin- final ok
|
Final | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | FAIL |
Brian Scoles
|
|
|
Bj 573 0755 Inspection requested via web by william kerwin- need secondary drain ran- firecaulk all penetrations- need to fix insulation on supply and return
|
Rough-in | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Teresa Costello- R/I ok
|
Rough-in | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | FAIL |
Ben Livingston
|
|
|
Bj 208 573 0755 Inspection requested via web by william kerwin need approved manual j onsite for inspection
|
Pressure Test | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Ben Livingston
|
|
|
Bj 208 573 0755 Inspection requested via web by william kerwin 20lb gas 5lb flue
|
Rough-in | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | NR |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Teresa Costello- still installing
|
Pressure Test | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | NR |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Teresa Costello- still installing
|
Issue PAID IN FULL permit | | | 2/20/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/20/2018 | | DONE |
|
|
|
This permit was created on the web by Teresa Costello
|