First Notice | 10/5/2018 | 10/5/2018 | 1/28/2019 | | DONE |
Chad Schwendiman
|
|
|
This permit finaled on the web by Dan Flaherty
|
Final | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Chad Schwendiman
|
|
|
Final inspection. Contact Francisco ###-####. TAB report will be emailed to you. Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Final | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | CANC |
Chad Schwendiman
|
|
|
Final inspection ; Francisco is your contact Phone #: ###-#### Inspection requested via web by Kim Adams - This was the wrong permit number
|
Final | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PART |
Chad Schwendiman
|
|
|
Francisco is your contact. Phone #: ###-#### Inspection requested via web by Kim Adams - Basement kitchen hood okay
|
Rough-in | 7/27/2018 | 7/27/2018 | 7/27/2018 | A | PASS |
Chad Schwendiman
|
|
|
Francisco is your contact Phone #: ###-#### Inspection requested via web by Kim Adams - Okay to cover grid ceilings 1st floor
|
Conference | 6/12/2018 | 6/12/2018 | 6/12/2018 | A | DONE |
Chad Schwendiman
|
|
|
Dale Pipkin is your contact for the conference. Phone #: ###-#### Inspection requested via web by Kim Adams - Met and discussed finishes around hood
|
Rough-in | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Chad Schwendiman
|
|
|
rough in inspection ; Francisco is the contact. Thank you! Phone #: ###-#### Inspection requested via web by Kim Adams
|
Rough-in | 3/30/2018 | 3/30/2018 | 3/30/2018 | P | PART |
Chad Schwendiman
|
|
|
Rough in inspection ; Francisco is your contact. Thank you! Phone #: ###-#### Inspection requested via web by Kim Adams - Okay to cover ductwork in shaft on 2nd floor
|
Issue PAID IN FULL permit | | | 3/30/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/30/2018 | | DONE |
|
|
|
This permit was created on the web by Kim Adams
|