Final | 5/17/2018 | 5/18/2018 | 5/17/2018 | A | PASS |
Jack Reynolds
|
|
|
Steve Phone #: ###-#### fireplace final ok
|
Final | 5/10/2018 | 5/14/2018 | 5/14/2018 | A | NR |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Kaila Martarano- fireplace needs to be finished- gas line outside needs to be supported every 6' across house
|
Pressure Test | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Kaila Martarano - 20lb gas pass
|
Pressure Test | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Kaila Martarano - Gas pressure fail Gauge was down below 20lbs
|
Rough-in | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Kaila Martarano - rough in on fireplace okay.
|
Pressure Test | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Kaila Martarano gas piping needs to be at least 3.5 inches above grade. need to re pressure test after fixing need to seal vent pipe termination with fire caulk
|
Issue PAID IN FULL permit | | | 4/5/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/5/2018 | | DONE |
|
|
|
This permit was created on the web by Kaila Martarano
|